[00:00:02] Speaker 02: Case number 16-7128, Hensel Phelps Construction Co. [00:00:07] Speaker 02: Appellate versus Cooper Carey, Inc. [00:00:09] Speaker 02: Ms. [00:00:10] Speaker 02: Stetson for the appellate, Mr. Shoemaker for the appellate. [00:00:40] Speaker 03: Good morning, Your Honors, and may it please the Court. [00:00:42] Speaker 03: My name is Kate Stetson. [00:00:44] Speaker 03: I represent the Appellant, Hensel Phelps Construction Company. [00:00:48] Speaker 03: This is a case presenting two different and classic contract law issues. [00:00:53] Speaker 03: Issue number one is whether the contract between Hensel Phelps and Cooper Carey was unitary or divisible. [00:00:59] Speaker 03: And issue number two is whether the indemnity clause in that contract covers [00:01:05] Speaker 03: the eight and a half or so million dollars that Hensel Phelps had to expend in order to remedy Cooper Carey's errors. [00:01:12] Speaker 01: Now, why have difficulty with your outset position? [00:01:18] Speaker 01: If one accepts your first statement of the issue, you're in better position than I think is the appropriate question. [00:01:27] Speaker 01: The question is whether or not the [00:01:34] Speaker 01: The plaintiff had a cause of action. [00:01:37] Speaker 01: earlier than the statute of limitations period, which may or may not involve a unitary or phased construction project. [00:01:53] Speaker 03: Judge Silverman, I think that's true to a point. [00:01:56] Speaker 03: I think though that the parties and the district court itself actually would agree that if this contract was a unitary contract, [00:02:04] Speaker 03: that the time for filing a lawsuit hadn't run. [00:02:08] Speaker 01: So if you look at Judge Leon's opinion... I looked at your opponent's brief, and they focused not on unitary versus divisible, they focused on when you had a cause of action. [00:02:21] Speaker 01: And indeed, as I look at the cases, [00:02:24] Speaker 01: It's sort of backwards. [00:02:26] Speaker 01: The courts look at unitary or divisible in order to determine whether there was an earlier cause of action. [00:02:33] Speaker 01: But if you have, wouldn't you agree if a contract specifically states that there is an earlier cause of action, it wouldn't be relevant as to whether it was a unitary or divisible contract? [00:02:46] Speaker 03: No, I think Judge Silverman, the question about whether there's a cause of action actually is inextricably tied with the unitary contract question, which is why I framed it this way. [00:02:56] Speaker 01: Well, let's say we have a contract that clearly is divisible. [00:03:04] Speaker 01: Nevertheless, there's a specific provision indicating that there's a right of cause of action at an early stage. [00:03:15] Speaker 03: Well, Judge Silverman, if the contract is divisible and there is a statement in the contract specifying that a cause of action may arise at an earlier stage, that actually is a quite different question than the one presented here. [00:03:28] Speaker 03: No, no, no. [00:03:29] Speaker 03: He said if it's unitary. [00:03:31] Speaker 03: He said if it's unitarian. [00:03:32] Speaker 03: Oh, I misunderstood. [00:03:34] Speaker 03: I thought you said it was a divisible contract presenting an earlier cause of action. [00:03:39] Speaker 01: The contract is unitary, which is your theory, but there is a statement that there is an earlier cause of action. [00:03:56] Speaker 03: In that event, I think, Your Honor, the contract wouldn't be unitary. [00:04:00] Speaker 03: I don't think those two things can coexist. [00:04:02] Speaker 03: But let me explain why, if I could. [00:04:04] Speaker 03: Judge Leon's opinion itself says, and this is Joint Appendix 377 to 378, when you have a unitary contract, first breach, so this notion of when the cause of action arises, [00:04:16] Speaker 03: first breach doesn't occur until the contract is substantially complete. [00:04:21] Speaker 03: And this is Judge Leon's quote, a unitary contract cannot be breached part way through the construction process, even where there are errors. [00:04:30] Speaker 01: I understand why you're quarreling with Judge Leon's opinion rather than my hypothetical. [00:04:37] Speaker 03: Judge Silverman, I think it's because your hypothetical presents a question that can't be answered respectfully. [00:04:44] Speaker 01: I think you're right. [00:04:46] Speaker 01: I think you're having a very difficult question on the answer. [00:04:49] Speaker 03: The idea that a contract is unitary, if that is in fact what the contract says, which is what this contract is, [00:04:57] Speaker 03: It can't provide for an earlier cause of action. [00:05:00] Speaker 01: The whole idea behind a unitary contract. [00:05:04] Speaker 01: As a matter of fact, doesn't this contract specifically provide that it can be an earlier cause of action? [00:05:09] Speaker 01: There is in the exact language it says that it can be an arbitration process or litigation earlier. [00:05:19] Speaker 03: Judge Silverman, it does make reference generally to litigation. [00:05:22] Speaker 03: I think the problem with that argument is that it ignores all of the other condition that DC law instructs a court to review when you look at whether a contract is unitary. [00:05:33] Speaker 03: Is this an entire contract? [00:05:34] Speaker 03: What is the contract for? [00:05:36] Speaker 03: So for example, Joint Appendix 17 and 15, what those pages of the Joint Appendix say is this is a lump sum contract [00:05:43] Speaker 03: for a course of work including completion and construction of the project. [00:05:48] Speaker 01: You're avoiding my concern with that specific language. [00:05:52] Speaker 01: And furthermore, I have another question, which really puzzles me that you did not respond to in the reply brief. [00:06:00] Speaker 01: What about the claim narrative that your client presented, which specifically stated that the breach of contract took place, the breach of standard of care took place at an early stage. [00:06:15] Speaker 03: Judge Silverman, that, in fact, is the fighting issue in this case. [00:06:18] Speaker 01: No, but that was your own client's claim narrative. [00:06:22] Speaker 03: I understand. [00:06:23] Speaker 03: The error, though... [00:06:26] Speaker 03: took place in an earlier stage. [00:06:28] Speaker 03: But in that claim narrative, you'll also see, among other things, that Cooper Carey attempted to remedy the error. [00:06:34] Speaker 03: It attempted to remedy the error, among other ways, by actually going back to the DC permitting authority and asking for an exception to the fire code that the DC authority had quoted. [00:06:45] Speaker 03: If that error had been remedied, which, by the way, is an express instruction in this contract, that that be permitted to take place in this unitary course of [00:06:55] Speaker 01: That would be always true that somebody could remedy a breach. [00:07:02] Speaker 01: That's got nothing to do with whether a breach took place. [00:07:04] Speaker 03: I think, Your Honor, we're having a debate between the existence of an error, or sometimes what's called a default under the contract, and the existence of a breach. [00:07:12] Speaker 03: But the entire question in this case is if first breach only occurs on substantial completion, which is DC law when it comes to a unitary contract, then the error that is committed earlier is not yet viewed as a breach. [00:07:28] Speaker 01: I apologize. [00:07:28] Speaker 01: Whatever DC law, [00:07:30] Speaker 01: deals with in a default situation, this contract is rather specific. [00:07:37] Speaker 01: And the claim narrative said the breach took place when the original documents were provided by the architect. [00:07:45] Speaker 03: Your honor, the claim narrative enumerates a number of errors that took place, some of them dating back to 2008, which is of course well before Hensel Phelps was even involved, some of them extending to 2012 and 2013. [00:08:02] Speaker 03: That's part of the problem that I think you're struggling with, which is when you are dealing with a multi-multi-million-dollar contract like this, there are going to be errors and defaults along the way. [00:08:16] Speaker 03: That's why Section 5 of the party's agreement actually provides for a process [00:08:21] Speaker 03: so that the parties can attempt to remedy those errors and those defaults before we get to the point of litigation. [00:08:28] Speaker 03: But one of the other things the claim narrative says, by the way, is there are 48 different deliverables in this contract. [00:08:36] Speaker 03: 48. [00:08:37] Speaker 03: And those deliverables, by the way, are divided into smaller categories as well. [00:08:41] Speaker 03: So if there is an error in a design, for example, in 2008 having to do with a preliminary design relating to the fire code, [00:08:50] Speaker 03: Does the contract breach term begin to run from 2008? [00:08:56] Speaker 03: Does it begin to run from the next construction design document that incorporates that error? [00:09:01] Speaker 03: How about the third one after that? [00:09:02] Speaker 01: The problem with this case is that all of those... Your opponent says that its latest is March 2011. [00:09:10] Speaker 03: Well, it's interesting that my point says that because you will look in vain actually in Judge Leon's opinion for the date that the breach of contract claim began to run. [00:09:21] Speaker 03: And I submit that's because the district judge was struggling with the same issue as well. [00:09:25] Speaker 03: At one point he says, [00:09:27] Speaker 03: the date began to run from when Hensel Phelps accepted the designs. [00:09:32] Speaker 03: But of course, that was just when Hensel Phelps stepped into Marriott's shoes. [00:09:36] Speaker 03: That date has no significance for a breach of contract claim. [00:09:39] Speaker 03: In other circumstances, judge for the nonsense. [00:09:42] Speaker 01: So in your view, the breach of contract was in 2008. [00:09:46] Speaker 03: No. [00:09:46] Speaker 03: In my view, the breach of contract was in April 1st of 2014. [00:09:51] Speaker 03: And the reason that that is the date is because that is the date that everyone understands that the certificate of substantial completion issued. [00:10:00] Speaker 03: And that's, you can find that in our complaint at Joint Appendix 9. [00:10:03] Speaker 01: I'd like to ask you a question about public policy. [00:10:08] Speaker 01: I was really mystified by the amicus brief and your arguments on public policy, since it seemed to me [00:10:15] Speaker 01: This could easily be solved by contract, including the tolling agreement. [00:10:22] Speaker 01: So in other words, contractors, who were of course the big guys, could always contract with the architect to make sure that there wasn't a cause of action until the end of the construction. [00:10:40] Speaker 01: or a tolling agreement, one or the other. [00:10:43] Speaker 01: This can easily be done by contract. [00:10:45] Speaker 01: So why do you want the courts to step in and help you solve a problem when you obviously have the capacity to contract as you wish? [00:10:57] Speaker 03: To begin with, the question whether this contract is a unitary contract is, I think, separate from whether the parties also could have provided a different way to make sure that the claims don't approve. [00:11:09] Speaker 03: I understand that. [00:11:10] Speaker 03: But when you were talking about a contract for provision of services, which runs through, and this is what Joint Appendix 17 says, completion and construction of the project, [00:11:21] Speaker 03: These parties understood that this was a unitary contract. [00:11:25] Speaker 03: D.C. [00:11:26] Speaker 03: law provides that this is a unitary contract. [00:11:28] Speaker 01: Council, I want to be asking about the public policy argument, which you make in your brief and which the amicus brief. [00:11:34] Speaker 01: That's correct. [00:11:35] Speaker 01: Why am I incorrect in saying, gee, why are we worried about public policy when the construction companies can always write a contract that solves their problem? [00:11:49] Speaker 03: I think, Your Honor, the presence of the amicus itself indicates the scope of this problem. [00:11:55] Speaker 03: Until this case, everyone understood, without regard to tolling agreements, which by the way of course require agreement from all sides, which according to Cooper Carey apparently would have to be entered into with every [00:12:08] Speaker 03: single identified error during the entire course of a contract. [00:12:13] Speaker 03: The public policy governing the idea of the unitary contract already has been in place. [00:12:19] Speaker 03: That's why the amicus came in this case in the first instance, to say if Judge Leon's opinion is right, [00:12:25] Speaker 03: If contractors actually have to sue for breach or somehow enter into tolling agreement after tolling agreement or sue and amend and amend and stay until the end of the project. [00:12:36] Speaker 01: One tolling agreement and do it. [00:12:37] Speaker 01: I could write it back in my office in 36 seconds. [00:12:42] Speaker 03: But Judge Silverman, the point of our public policy argument is that when you look at the question about when a statute of limitations starts to run, and you look at the notion of the unitary contract, one of the things that you ask yourself is, what did the parties intend when they entered into this contract? [00:13:00] Speaker 03: Our point is, when you look at the four corners of this contract, not what might have been or what they might have written, but it was the four corners of this contract [00:13:09] Speaker 03: you come away with the understanding that this is a unitary form of contract. [00:13:13] Speaker 04: And isn't it always true that in a contract case, when we look at a contract and we think, did this or did this not provide for this situation, we look up to the sky and think, gosh, I wish they had expressly anticipated this and written it in. [00:13:27] Speaker 04: I mean, that's endemic in contract law, that we're gonna have situations where it could have been solved easily, but it wasn't, and it isn't, because of what you say about understandings in background law. [00:13:37] Speaker 03: And that's why I think the DC courts consistently have said, when you look at this contract, when you're trying to figure out after the fact, when an issue comes up about whether this document is unitary or divisible, what do you look at? [00:13:50] Speaker 03: You look at lump sum, [00:13:52] Speaker 03: you look at whether this is the whole agreement, you look at whether it was entered into at different times, all of those indicia point to the same result here. [00:14:01] Speaker 04: And whether in the stages the compensation and a deliverable are matched, which as I read the record, they aren't here, what do you think the reference to litigation that you and Judge Silverman were referring to means? [00:14:17] Speaker 03: I think because it's such a general statement, it really could mean any number of things. [00:14:26] Speaker 03: It could mean, for example, if there is a dispute implicating a subcontractor under the contract that has [00:14:33] Speaker 03: implications for payment, when payment is made and to whom, provided, I assume, that Article 5's prescriptions and prescriptions in terms of who gets to suspend and when they have to notify and terminate, provided that all of those things have been taken care of, you could imagine a circumstance where there's a payment dispute that gives rise to litigation, but there is still an obligation on one or the other party to perform. [00:14:57] Speaker 03: But that single phrase, the idea that this contemplates litigation, therefore this unitary contract somehow becomes divisible, that is completely unsupported by the rest of this document. [00:15:10] Speaker 01: Counsel, you understand, my understanding is it doesn't have to be divisible. [00:15:15] Speaker 01: That it's an artificial division in this case to talk about unitary and divisible. [00:15:21] Speaker 01: That courts do that when there's no other indication as to whether the cause of action is earlier. [00:15:28] Speaker 03: Judge Silverman, I'm not sure that that's accurate, because the way that courts approach the unitary versus divisible issue is to look at the contract for all of those indicia I mentioned. [00:15:39] Speaker 03: That's what the Holliday-Holmes case says. [00:15:41] Speaker 03: That's what the Durham versus Howard case says. [00:15:43] Speaker 01: But there is no indication of other indications of cause of action earlier. [00:15:49] Speaker 01: You still haven't answered the claimed narrative, but that was, it seems to be a devastating [00:15:55] Speaker 01: point there, page 12, 13, and 14 of the Pelley's brief when they point out, hey, the claim narrative specifically asserted the breach here took place early on. [00:16:09] Speaker 03: Judge Silverman, the problem with that though is the very problem that we're talking about, which is when the claim narrative asserted all of those errors, errors that began in 2008, some errors that were committed in 2012 or 2013. [00:16:24] Speaker 01: No, it wasn't an error. [00:16:27] Speaker 01: It was stated as a breach of duty of standard of care, which means a breach of contract. [00:16:33] Speaker 03: Only if this contract was somehow divided into dozens and dozens and dozens of pieces. [00:16:41] Speaker 03: That's the problem. [00:16:42] Speaker 03: The idea that the claim narrative, which, by the way, was a document that was submitted to Cooper Carey years after this agreement, was struck, that the claim narrative somehow bears on whether this document was or was not unitary, doesn't add up with the— Well, I said there was an admission against interest, was it not? [00:16:58] Speaker 03: No, I don't believe it was at all. [00:17:00] Speaker 04: Isn't there a distinction between a breach of the standard of care and a breach of the contract? [00:17:09] Speaker 04: I mean, as I understand this going over time, that both parties are inquiring of the other. [00:17:16] Speaker 04: Have you met the standard of care that our contract requires? [00:17:22] Speaker 04: I'm going to raise it with you and show you that you haven't met it, because if you don't by the end of the day fix that, there's going to be a contract claim. [00:17:31] Speaker 04: And so it's in a period of time of saying, well, look, you've fallen short on this. [00:17:36] Speaker 04: You haven't done this. [00:17:37] Speaker 04: This wasn't to specifications. [00:17:40] Speaker 04: We need this to be redone. [00:17:42] Speaker 04: And that over time, there are going to be a lot of instances in which somebody is identifying a breach of the standard of care that is not [00:17:51] Speaker 04: the same as a breach of contract, per se. [00:17:54] Speaker 01: I think that's right, and I think the fact that the parties— Do you think it's so right that you're sorry you didn't make the argument yourself? [00:18:02] Speaker 03: I believe I did make this argument in this way. [00:18:04] Speaker 01: I don't think you did, counsel. [00:18:06] Speaker 03: I did make this argument because at Section 5 of the agreement itself, it provides for the very iterative process that Judge Pillard is talking about. [00:18:16] Speaker 03: It provides that if there is an error identified or, as the claim narrative puts it, a breach of the standard of care, that's when the parties... You never responded to the claim narrative argument at all. [00:18:29] Speaker 03: Judge Silberman, that's because the claim narrative, because it arose years after the contract, because it is a document that is the standard exemplar to use when you get to the end of a project, when the project is substantially complete, and there remain either errors that were unremitted or costs that have not yet been paid, this is the document that you create. [00:18:54] Speaker 03: The idea that using the word breach [00:18:57] Speaker 03: in the claim narrative somehow means that this agreement that Hensel Felt stepped into in 2010 becomes a divisible agreement is not supported by any case that I have ever come across in preparing for this argument. [00:19:12] Speaker 01: It doesn't have to be divisible. [00:19:17] Speaker 03: Judge Silberman, respectfully, it does. [00:19:20] Speaker 03: The issue is whether this contract is unitary or divisible. [00:19:24] Speaker 03: If it's unitary, the time has not run. [00:19:27] Speaker 03: If it is divisible, it is not. [00:19:29] Speaker 03: And all of your questions, whether they go to the claim narrative, whether they go to the nature of the party's agreement within the contract, [00:19:36] Speaker 03: whether they go to the method of resolving disputes that come up during the course of this project, all the way through to completion of construction, all of those are just different ways of asking this core question, whether this contract is unitary or divisible. [00:19:51] Speaker 02: So is it your position that if the contract is unitary, then there is no language that the parties could put into the contract that would require some earlier action? [00:20:08] Speaker 03: I think, Judge Brown, that's akin to the question that Judge Silberman posed earlier. [00:20:12] Speaker 02: Well, it is, because I'm trying to get at the same thing. [00:20:14] Speaker 03: Yes. [00:20:14] Speaker 03: If the contract is unitary... [00:20:17] Speaker 03: it by nature can't provide for an earlier cause of action to arise. [00:20:23] Speaker 03: And that's the difference that we've also been discussing between an error, a default, a breach of the standard of care, and an action for breach of contract. [00:20:31] Speaker 03: And by the way, this is something that even Judge Leon understood. [00:20:35] Speaker 03: Judge Leon, whom we are appealing and with whom we disagree in many other respects, understood that when you have a unitary contract breach, [00:20:43] Speaker 03: actionable breach doesn't happen until the end of that contract, until April 1st of 2014. [00:20:49] Speaker 02: Well, earlier, I thought that you agreed with Judge Pillard that often when we're trying to figure out what's going on in a contract, one of the things that we say is, oh, if only they had specifically anticipated this and put that language in the contract, right? [00:21:04] Speaker 02: But now, if I understand what you're saying, it's that once you are [00:21:09] Speaker 02: into this paradigm that is the unitary contract, nothing that the parties want to do can ever take you out of that. [00:21:19] Speaker 03: Well, I think here's how I would bridge those two questions. [00:21:24] Speaker 03: The first is every if only post-hoc situation gives rise to the kind of contract interpretation case that we're talking about here. [00:21:35] Speaker 03: That's why contract interpretation cases I think exist. [00:21:38] Speaker 03: I took Judge Pillard's question and observation to be [00:21:42] Speaker 03: that if the parties had intended for the contract to be divisible, they could have structured it in a different way. [00:21:50] Speaker 03: If the parties had intended for it to be unitary, in addition to making it for a single project, in addition to making it through completion of construction, in addition to making it a lump sum, and in addition to it being a single document, [00:22:04] Speaker 03: They also could have said, for example, at the end, we intend that this contract be unitary. [00:22:09] Speaker 03: That would have been terrific. [00:22:11] Speaker 03: That would have saved us all a lot of time. [00:22:13] Speaker 03: They didn't. [00:22:14] Speaker 03: So what we're left to fall back on are the sorts of factors that the DC courts instruct you to look at when you're trying to determine whether this single obligation can be sliced into dozens and dozens of different statute of limitations or whether it's one that stems from substantial completion. [00:22:32] Speaker 03: If I could spend just a minute on indemnity, I'd appreciate it. [00:22:37] Speaker 03: Because this is a separate issue and a separate statute of limitations. [00:22:40] Speaker 04: Let me just ask you, if you were to prevail on your unitariness claim, do we need to reach the indemnity? [00:22:49] Speaker 04: No, you do not. [00:22:51] Speaker 03: If we prevail on the unitary contract claim, all of these breach of contract claims are timely, and I think that the parties and even Judge Leon would agree on that. [00:23:02] Speaker 03: On indemnity, here is the problem I think that the panel has to confront. [00:23:07] Speaker 03: What Judge Leon held in his opinion was that this broad indemnity clause only applied to third-party litigation. [00:23:16] Speaker 03: He says it twice in his opinion. [00:23:18] Speaker 03: Not even Cooper Carey is defending that on appeal. [00:23:22] Speaker 03: What Cooper Carey is now saying is, yes, the indemnity provision applies to third-party claims, but Pencil Phelps's claims are first-party claims. [00:23:31] Speaker 03: They are not. [00:23:32] Speaker 03: Hensel Phelps' claims, roughly about $7.2 million of the $8.5 million, are third-party expenses, and that's where the claim narrative actually has great utility, Judge Silverman, because if you look at the claim narrative, you see a detailed recitation of every single payment made to every single third-party contractor [00:23:56] Speaker 03: resulting in those claims for indemnity. [00:23:58] Speaker 03: Those payments, by the way, were not made until 2012 and 2013. [00:24:04] Speaker 03: So if you reach the indemnity issue at all, finding number one has to be that Cooper Carey agrees that it applies at least to third-party claims. [00:24:14] Speaker 03: And that takes care of over $7 million of the $8.5 million that we're talking about. [00:24:19] Speaker 03: Finding number two has to be with respect to the small amount of claims or expenses that Hensel-Felps itself incurred. [00:24:29] Speaker 03: So expenses for additional overhead, administration, additional time spent on the project that they hadn't budgeted for, all of those things. [00:24:37] Speaker 03: You will look in vain in this indemnity provision for any kind of limitation on the first party claim. [00:24:43] Speaker 03: The indemnity provision, it's actually hard to imagine a provision that could contain more broad phrases that we're all familiar with. [00:24:51] Speaker 01: Can you say, your first point, with respect to the damages that [00:25:00] Speaker 01: that Henselfelps suffers. [00:25:07] Speaker 01: You say they're a third party because they involve costs that Henselfelps had to pay other people to fix. [00:25:17] Speaker 03: Yes, yes. [00:25:19] Speaker 03: Expenses, claims that were essentially submitted to Hensel-Felps by... Well, that would be true in any first party claim, isn't it? [00:25:24] Speaker 01: Isn't that true? [00:25:25] Speaker 03: I think that the difference that I would draw, to the extent there is a difference between first and third party, is with respect to that over $7 million of costs, these were expenses that were charged to Hensel-Felps by [00:25:37] Speaker 03: the cement contractor, by the fire extinguisher contractor, by all of the contractors that are listed in the statement plan. [00:25:44] Speaker 01: If I could not answer my question, though, I was trying to think about what would be the – let's suppose there was clear distinction here between first and – first party claims. [00:25:58] Speaker 01: Wouldn't all first party claims involve some costs that would go out to third parties? [00:26:04] Speaker 01: No, I think it's... I think it is... Aren't you confusing the situation here? [00:26:10] Speaker 03: Well, I think there is probably a way, and this is, of course, not something that Judge Leon got into, because he concluded this only... This is all to know, though, isn't it, counsel? [00:26:19] Speaker 01: Absolutely. [00:26:23] Speaker 01: Judge Leon's opinion doesn't help you necessarily up here. [00:26:28] Speaker 03: No, I mention it only because Cooper Carey has agreed with us on this third-party point. [00:26:33] Speaker 03: Your question, though, about whether or the dividing line between first and third-party claims, the first-party claims such as they are that we would identify are expenses that Hensel Phelps itself incurred as a company, so the administration and the overhead. [00:26:49] Speaker 03: Your question, though, I think is [00:26:51] Speaker 03: even those expenses presumably were paid out to someone or something, a Hensel Phelps employee. [00:26:56] Speaker 05: Exactly. [00:26:57] Speaker 03: So if you take that broad reading, then, you know, the expenditure that Hensel Phelps is still making is a third-party expenditure because it's paying someone else. [00:27:06] Speaker 01: Another way of looking at it is all first-party claims involve some kind of third-party call. [00:27:12] Speaker 04: And that's just puzzling because then what's the function of an indemnity clause as distinct from breach of contract? [00:27:18] Speaker 04: There has to be some [00:27:20] Speaker 04: some limiting principle? [00:27:22] Speaker 03: I'm not sure. [00:27:23] Speaker 03: Well, there is certainly one limiting principle, and only one, in this indemnity provision. [00:27:28] Speaker 03: And that's the principle that comes at the very end, which says you can't be indemnified if you yourself were negligent. [00:27:35] Speaker 03: And you do have cases, and we cite them in our brief, involving situations where an indemnity was negligent and still got paid. [00:27:44] Speaker 01: Well, that would be true about the basic claims, too. [00:27:48] Speaker 01: I'm not sure that it will be true for the basic claims, but I think the distinction is... If in fact the facts were different in this case, that it was Hansel Phelps that was largely responsible or partly responsible for ignoring [00:28:09] Speaker 01: fire department, then their negligence would cut against any claim. [00:28:15] Speaker 03: I see what you're saying. [00:28:16] Speaker 03: And I think in a comparative or contributory negligence regime, maybe that would cut against a claim. [00:28:23] Speaker 03: The point I thought that Judge Pillard was making is, what's the limiting principle in this indemnity provision? [00:28:28] Speaker 03: That's the one. [00:28:29] Speaker 03: Everything else in this particular indemnity provision, you can imagine it being written a different way. [00:28:35] Speaker 03: And in fact, many of them are written a different way. [00:28:38] Speaker 03: But this indemnity provision says, among other things, to the fullest extent permitted by law, any and all claims, costs, expenses, damages, liabilities, as a result of or as a consequence of, including but not limited to. [00:28:52] Speaker 03: You can't find another broad phrase that's not in this indemnity provision. [00:28:57] Speaker 04: I think what I'm asking is, isn't there [00:29:01] Speaker 04: principle limitation is in the very concept of indemnity. [00:29:05] Speaker 04: And I'm trying to understand if you said, here's a contract, I'm gonna do this, I'm gonna build a building for you, and it was two cents contract, and I'm gonna indemnify you for any harm by the people that I bring in to build the house. [00:29:22] Speaker 04: and they have different sexual limitations. [00:29:24] Speaker 04: You typically would think that the identification is about somebody comes in and runs over your dog on the way in. [00:29:33] Speaker 04: You don't typically think of it as something that swallows or almost swallows or substantially overlaps with the breach harms. [00:29:40] Speaker 04: Right. [00:29:40] Speaker 03: You don't typically think of it that way. [00:29:42] Speaker 03: But even in your question, Judge Pillard, one of the things that you said was, I'm going to identify you if someone comes in and during the course of the project does harm. [00:29:52] Speaker 03: Many of the indemnity provisions that we see involve that kind of limitation. [00:29:58] Speaker 03: I will indemnify you if a third party files a claim against you or submits an expense report to you or requires you to pay out a liability. [00:30:06] Speaker 03: But the First Circuit, in the case that we cite in our opening brief, [00:30:10] Speaker 03: was presented with a really similar issue. [00:30:12] Speaker 03: A case came up to the First Circuit. [00:30:14] Speaker 03: The district judge said an indemnity provision can't possibly cover a first-party indemnity. [00:30:19] Speaker 03: That's not what an indemnity revision is. [00:30:21] Speaker 03: And what the First Circuit said is, indemnity just means you're paying somebody back for something. [00:30:27] Speaker 03: And if the indemnity provision is written in such a way that it doesn't exclude first-party claims, first-party claims are contemplated within the indemnity provision. [00:30:36] Speaker 03: So you can, of course, in response, Judge Piller, to your earlier question, you can get at this entire case by resolving it on that first statute of limitations unitary contract question. [00:30:48] Speaker 01: The indemnity question only comes up then in the circumstance where... What are the, excuse me, what are the damages that wouldn't be included by the indemnification provision under your theory? [00:31:01] Speaker 03: Under our theory, the indemnification provision, because it is so broad, [00:31:07] Speaker 03: likely contemplates all of the damages that we sought. [00:31:10] Speaker 03: But the reason I say likely contemplates is because there are damages arising from things like, and you see this at the very end of the claim narrative, general and administrative expensive, profit markup, those types of damages which are calculated based on the other expenses, you could see those as being one step removed from a third party expense. [00:31:35] Speaker 03: However, all of those, of course, are damages and damages are covered by them. [00:31:39] Speaker 01: So, therefore, the indemnification clause is your total, its purpose is your total relief against the architects. [00:31:53] Speaker 01: That's the purpose of it. [00:31:54] Speaker 01: That's the total relief against the architects if they do any breach. [00:31:59] Speaker 03: This indemnification clause, the short answer is yes with one qualifier, and that's the qualifier that if Hensel-Felps is negligent, it can't recover. [00:32:08] Speaker 01: Of course, that would be true under any circumstances. [00:32:10] Speaker 03: But this indemnification clause provides for total relief because of the way that it's written on it. [00:32:16] Speaker 01: So that's the total damage clause. [00:32:17] Speaker 01: That's the total damage clause for the contract. [00:32:19] Speaker 03: Yes, of course, the way that Judge Leon's opinion approached the issue, he dealt with it just in terms of third-party litigation. [00:32:27] Speaker 01: So this question about whether there... In other words, in answer to Judge Pullard's question, there is no principle limit to this indemnification clause. [00:32:40] Speaker 03: Judge Silberman, the limit to the indemnification clause is the one that's baked into it. [00:32:48] Speaker 03: But that doesn't mean, you just said there's no principled limit. [00:32:51] Speaker 01: That doesn't mean it's... No, no, that was Judge Willard's question. [00:32:54] Speaker 01: Was there a principled limit on this indemnification clause? [00:32:58] Speaker 03: Well, the answer is that the indemnification clause is as broad as you can write it, to the fullest extent permitted by law, and so on and so forth. [00:33:09] Speaker 01: It's a funny reading of a contract, where the whole damage clause provision is in the indemnification clause. [00:33:15] Speaker 03: Well, the reason I think that it poses such a conundrum here is because, of course, the indemnification claims arose [00:33:25] Speaker 03: in 2012 and 2013 if you look at the claim narrative and all the documents attached to it. [00:33:30] Speaker 03: So the time bar issue that is present or so the district court said with respect to the first breach of contract claim doesn't exist with respect to the indemnity claim. [00:33:41] Speaker 03: If we are right though on the breach of contract claim that it didn't start running until substantial completion, [00:33:46] Speaker 03: You don't need to reach the indemnity issue at all. [00:33:49] Speaker 01: Now, of course, if you're wrong on the breach of contract claim, then you pour the whole breach of contract claim into the indemnification claim. [00:33:57] Speaker 03: That's correct, because of the way that this particular indemnity provision was written. [00:34:02] Speaker 03: Yes, it could have been written another way, but it was written in such a way as to contemplate all of these damages. [00:34:09] Speaker 03: All right, if there are no further questions. [00:34:10] Speaker 03: Thank you, Your Honor. [00:34:20] Speaker 00: Good morning, Your Honors. [00:34:21] Speaker 00: May it please the Court? [00:34:22] Speaker 01: You can raise that instrument, whatever the hell you call it. [00:34:29] Speaker 00: I appreciate that, Your Honor. [00:34:31] Speaker 00: My name is Jonathan Shoemaker, and I represent Cooper Carey in this matter. [00:34:36] Speaker 00: The district court properly dismissed Hensel-Felps' stale claims for breach of contract and indemnity, and in so doing enforced the settled law of the District of Columbia and honored the party's bargained for expectations. [00:34:50] Speaker 00: Cooper Carey asked this court to affirm the district court's ruling. [00:34:54] Speaker 00: The first issue on appeal deals with the statute of limitations, and I think you understand our brief clearly. [00:35:00] Speaker 00: The statute of limitations question begins with the statute of limitations language itself, which in this particular instance is instructive. [00:35:09] Speaker 00: The DC statute of limitations required that Hensel-Felkes file a complaint for breach of contract within three years, quote, from the time the right to maintain the action approves. [00:35:21] Speaker 00: The issue on appeal is simple. [00:35:24] Speaker 00: When did Hensel Phelps have the right to maintain a cause of action for breach of contract against Cooper Carey? [00:35:34] Speaker 00: We argue, consistent with the law of the District of Columbia, [00:35:38] Speaker 00: that Hensel Phelps had the right to maintain a breach of contract at the time of first breach in October of 2010 when the preliminary documents were first adopted as part of Hensel Phelps' contractual obligation. [00:35:52] Speaker 01: What do you take to be the response to your colleague's argument that the key to this case is whether it's unitary [00:36:01] Speaker 01: or divisible, the contract, that is. [00:36:04] Speaker 00: Respectfully, I disagree entirely. [00:36:06] Speaker 00: The D.C. [00:36:06] Speaker 00: Court of Appeals has never recognized the distinction between unitary or divisible contracts for the purposes of approval of claims for statute of limitations purposes. [00:36:18] Speaker 00: All of the cases cited that have discussed any type of distinction do not come out of the D.C. [00:36:25] Speaker 00: Circuit. [00:36:25] Speaker 00: And the D.C., or sorry, the D.C. [00:36:26] Speaker 00: Court of Appeals. [00:36:28] Speaker 00: The DC Court of Appeals has a general rule, which is that breach occurs at the first breach, and that's the capital place case. [00:36:37] Speaker 04: But it seems like it's almost tautological. [00:36:39] Speaker 04: If you're saying that the contract can be and was breached such that a claim accrued before substantial completion, that's another way of saying that the contract isn't unitary, and that's your position. [00:36:56] Speaker 04: So your position is that it's not a unitary contract, at least if you want to be talking to rather than pass one another. [00:37:03] Speaker 04: the parties, right? [00:37:04] Speaker 04: So whether you call it divisible or whether you say claim accrued during the building and design and building of the building, it's the same thing. [00:37:15] Speaker 00: That's correct. [00:37:16] Speaker 00: The DC Court of Appeals, however, has expressly addressed a unitary contract and concluded that the existence of continued contractual obligations under a contract does not postpone the accrual of a claim for first breach purposes. [00:37:32] Speaker 00: That's the case of Wright versus Howard University. [00:37:34] Speaker 00: Right. [00:37:34] Speaker 01: Counsel, your response to Judge Pillard was not yes, it was no. [00:37:42] Speaker 01: You just explained why under D.C. [00:37:45] Speaker 01: law it could be unitary, but it also could be an earlier cause of action. [00:37:51] Speaker 01: Absolutely. [00:37:51] Speaker 01: So you shouldn't have answered yes and then no. [00:37:55] Speaker 00: I apologize. [00:37:55] Speaker 00: It doesn't matter whether the contract is divisible or unitary for the purposes of approval for a claim under a contract in the District of Columbia. [00:38:04] Speaker 04: And you're claiming that the Howard University case dealt with a unitary contract, but that there was a claim that accrued before? [00:38:12] Speaker 00: Whether the contract was unitary or divisible, in the Howard University case, it dealt with a tenure-track professor. [00:38:18] Speaker 00: And so there is no divisible component to it. [00:38:21] Speaker 00: I was using it by analogy because they've been arguing this unitary theory. [00:38:25] Speaker 00: In the Howard University case, the professor alleged in the complaint [00:38:30] Speaker 00: that the breach occurred when Howard University failed to conduct a tenure review. [00:38:35] Speaker 04: Right, but I mean, that's a very different circumstance. [00:38:37] Speaker 04: And I think the notion of a unitary contract isn't even raised in that case. [00:38:41] Speaker 04: The other Howard University case seems more relevant, which is DC Court of Appeals, Howard University versus Durham, which does talk about the factors that determine whether a contract is unitary, one being, is there a single agreement? [00:38:56] Speaker 04: Second, is there a single consideration? [00:38:57] Speaker 04: And the third, it seems to me, is what [00:39:00] Speaker 04: is troubling because there are these phases in this contract and I do see that as potentially creating different moments when you have to kind of look back and assess and say do we have anything, any breach and are we gonna sue before you move on and I take that to be your argument. [00:39:19] Speaker 04: But one of the things that the Howard University versus Durham case says is that the third factor is basically the contract has to be divisible and there's [00:39:29] Speaker 04: compensation given for something being completed. [00:39:33] Speaker 04: And here, the compensation is being given monthly, and phase one is not all sort of paid sign sales and delivered. [00:39:40] Speaker 04: It's a more rolling and not matched up set of exchanges. [00:39:45] Speaker 00: But that Howard University case that distinguishes between Unitarian and Visible is not an accrual case. [00:39:50] Speaker 00: It just talks about different types of contracts and whether or not his resignation as a dean also was the equivalent of a resignation of his tenure as a professor, as a tenured professor of the faculty. [00:40:01] Speaker 00: And that did not address accrual provisions, which takes me back to the original point, which is the DC Court of Appeals has but one rule for the accrual of breach of contract claims, and that is first breach. [00:40:15] Speaker 04: But that again seems a tautology, first breach that begs the question, was it a breach? [00:40:22] Speaker 04: How do we know? [00:40:23] Speaker 04: Somebody's fallen short of the standard of care. [00:40:25] Speaker 04: It cannot be in a construction relationship, design and construction, which takes place over years and is extremely complex, that every time one party falls short of fulfilling its standard of care, [00:40:42] Speaker 04: a contract claim accrues. [00:40:43] Speaker 04: It cannot be. [00:40:45] Speaker 00: Respectfully, that's what the DC Court of Appeals has said. [00:40:49] Speaker 00: And the question is... Where? [00:40:50] Speaker 00: Your best case. [00:40:51] Speaker 00: The best case is capital place. [00:40:52] Speaker 00: And where it says that in capital place, it's in the context of a construction contract, where a contractor has until the completion of the project to deliver the project in conformity with the contract documents. [00:41:04] Speaker 00: Hensel Phelps' argument is that in this particular case, the design documents were not, the time for delivery and acceptance, and that's from their reply brief on page 5, they finally synthesized the argument, the time for delivery and acceptance of the design documents was not until substantial completion. [00:41:20] Speaker 00: And that's contrary to the terms of the design agreement, which is inevitably contrary and different from a construction contract, [00:41:27] Speaker 00: which called for the design to be delivered in phases. [00:41:31] Speaker 00: The preliminary phases and the preliminary design documents were delivered to the owner and in fact accepted as is without a representation from Hensel Phelps when they agreed to assume the contract. [00:41:43] Speaker 04: And how much, so it sounds like a bit of your case rests on the fact that Hensel Phelps took something over and took it over as is. [00:41:52] Speaker 04: And they basically are given, here's some documents and it's on them to say, well, do their due diligence and say, is this up to code? [00:42:02] Speaker 04: Does this have the, [00:42:05] Speaker 00: That is an issue that if this were to be remanded would be certainly a point of contention. [00:42:11] Speaker 04: But that's not, you're not sort of saying this is like design-bid-build as a result of that. [00:42:15] Speaker 04: It was a design-bid-build. [00:42:16] Speaker 04: As a result of that in particular. [00:42:19] Speaker 00: This contract was a design-bid-build contract at the time that it was formed. [00:42:23] Speaker 00: This contract was never contemplated as being a design-build contract, and even the AGC amici recognized that if this was a design-build contract, which it was at the time of formation, that we would prevail and Hensel Phelps would be wrong. [00:42:38] Speaker 00: In this particular instance, when Hensel Phelps took over the preliminary documents, they didn't agree to accept delivery of the final construction documents at substantial completion. [00:42:48] Speaker 00: Article 3 of the design agreement includes a specific schedule of services to be provided. [00:42:53] Speaker 00: And that schedule of services included the provision of final construction documents, which according to their claim narrative, [00:43:00] Speaker 00: were delivered on April 13, 2012, more than three years before the lawsuit was filed in this matter. [00:43:07] Speaker 00: But that doesn't matter. [00:43:08] Speaker 00: The point is that Hensel Phelps had an obligation to take those final construction documents and then deliver them to the owner for the owner's review and approval and take those final construction documents and get those final construction documents permitted before they could actually erect the building itself. [00:43:28] Speaker 00: And so all of the construction documents, the final construction documents, which under the construction contract itself became a contractual obligation for Hensel Phelps to meet well before substantial completion, occurred earlier than substantial completion. [00:43:44] Speaker 04: Is it your position that there are five times corresponding to the five stages when breach could occur, or that there are infinite times? [00:43:53] Speaker 04: How many moments of claim accrual [00:43:57] Speaker 04: One, first breach. [00:44:00] Speaker 04: No, no, because there are going to be breaches that happen after that. [00:44:03] Speaker 04: Well, there could be additional breaches that occur after that. [00:44:06] Speaker 04: And then what happens to those? [00:44:07] Speaker 04: You have to amend your complaint? [00:44:08] Speaker 01: Well, you're assuming that... Are you bringing suits? [00:44:10] Speaker 01: Well, isn't there a case on that? [00:44:12] Speaker 01: As I seem to recall, a case somewhere where a court pointed out that the cause of action [00:44:20] Speaker 01: accrues at the first breach, and then subsequent breaches can be covered in the same cause of action? [00:44:28] Speaker 00: Absolutely. [00:44:29] Speaker 00: And that's, I believe, the Colbert case, which says all you need to know is how the fact of injury. [00:44:33] Speaker 00: You don't need to know the full measure of their damages. [00:44:35] Speaker 00: And that's really what Hensel Phelps is arguing, is we didn't know the full measure of our damages until substantial completion. [00:44:41] Speaker 00: So although we knew that the breach occurred, we knew, and it's undisputed in the claim narrative, that the breach occurred in March of 2011, [00:44:50] Speaker 00: They then bore the costs and immediately, according to the claim narrative, began making changes in the field and implementing and incurring additional costs, which they were tracking, and there's correspondence cited in our brief, that they were tracking the costs associated with these issues as early as early 2012. [00:45:09] Speaker 00: And that their position is that they were obligated, taken to its logical conclusion, that they didn't have a right to file a lawsuit. [00:45:18] Speaker 00: And that's what the statute of limitations says, is that it's when you have a right. [00:45:22] Speaker 00: And the first question is you file, and then you have a variety of options if you're up against the statute of limitations and you file immediately. [00:45:30] Speaker 00: You can seek a stay if you believe this is a complex construction project. [00:45:34] Speaker 00: Before filing suit, you could seek a tolling agreement that could be drafted in 36 seconds. [00:45:41] Speaker 00: Or more fundamentally, as a sophisticated contractor, knowing the complexities of a construction project, you could negotiate to have an accrual provision in your contract itself that calls for the accrual of claims at substantial completion. [00:45:57] Speaker 00: And as noted in our brief, this is a very type of clause that has been negotiated in the construction industry for over 30 years. [00:46:05] Speaker 00: Hensel Phelps chose not to insist upon such an accrual provision, and in so doing, accepted the risk. [00:46:12] Speaker 00: They're a contractor. [00:46:13] Speaker 00: Who better than a contractor to use contracts to manage their risk? [00:46:18] Speaker 00: Hensel Phelps's position is also, as you noted earlier, contrary to the terms of the design agreement. [00:46:24] Speaker 00: The parties did contemplate the possibility that litigation could occur during the project. [00:46:30] Speaker 00: And respectfully, I don't believe that the provision, which is Article 7.09.5, could be read as relating to any type of litigation other than litigation between the parties. [00:46:44] Speaker 00: The entire section, subsections 1, 2, 3, and 4, all address the stepped dispute resolution procedure to take place between the parties. [00:46:53] Speaker 04: But that's a mediation process, and I find that to be wholly compatible with Hempstead Phelps' position, because you have an ongoing process, you want to work out who's obligation to do what, and so we can get it done, we're gonna mediate, and we're gonna figure out, are you gonna do this, or is this gonna require a change order, is this under the existing contract or not? [00:47:16] Speaker 04: Do that kind of dispute resolution, and then if you can't resolve it, [00:47:20] Speaker 04: there's gonna possibly have to be litigation, but you don't even know whether there's gonna have to be litigation because a lot of the things that look terrible when a relationship is ongoing get fixed. [00:47:31] Speaker 04: So it seems, I mean, the argument that seemed compelling to me in the AJC, in the Association of General Contractors, AJC brief, is that it seems to sort of, [00:47:44] Speaker 04: create a lot of need to file cases that might be unnecessary to have the first breach rule. [00:47:54] Speaker 00: The first breach rule, as we've articulated, has been the law in the District of Columbia for decades, has been the law in the Commonwealth of Virginia and Maryland, and the courts are not flooded with these types of claims. [00:48:08] Speaker 00: Owners routinely seek to modify contractual provisions and manage these risks, [00:48:12] Speaker 00: It's common to enter into tolling agreements. [00:48:15] Speaker 00: And as it relates to the stepped dispute resolution process, there's certainly always the opportunity for the parties recognizing the complexity of a project to say, gee, instead of fighting about this in court, let's put a pin in this and move forward. [00:48:30] Speaker 00: But the dispute resolution procedures does not call for putting a pin in it automatically. [00:48:35] Speaker 00: There is no automatic tolling provision that was contracted as part of this design agreement. [00:48:40] Speaker 00: So as a consequence, the parties, as a final dispute resolution procedure, referred to litigation. [00:48:46] Speaker 00: And they contemplated the possibility that whatever the issue was, it would not in fact be resolved prior to the substantial completion of the project. [00:48:55] Speaker 00: And they foresaw the possibility that there could be litigation. [00:49:02] Speaker 01: there would still be the obligation to continue to comply with the contract. [00:49:07] Speaker 00: Absolutely. [00:49:07] Speaker 00: Even while litigation was ongoing. [00:49:10] Speaker 00: Absolutely. [00:49:11] Speaker 00: And that's why we come back to the first breach rule and the discovery rule. [00:49:14] Speaker 00: The discovery rule, the DC Court of Appeals, and this court is of course tasked with applying what the law is, not what the law should be, but the DC Court of Appeals has used the discovery rule [00:49:25] Speaker 00: as an outside time frame for discovering first breach. [00:49:28] Speaker 00: That would take you to March 11. [00:49:30] Speaker 00: March of 2011, correct. [00:49:31] Speaker 00: And here, even the AGC amici, in advocating for adoption of Hensel Phelps's position, acknowledged that they were advocating for what the law should be, not what the law is, which is accrual at first breach or at the absolute latest discovery. [00:49:49] Speaker 00: Accordingly, we ask that the court affirm the district court's ruling on the breach of contract action. [00:49:55] Speaker 00: As it relates to the indemnity second count, the court need not reach this second issue because Hensel Phelps did not appeal the district court's conclusion that the indemnity claim, like the breach of contract claim, was barred by the statute of limitations. [00:50:10] Speaker 00: And I would note that part of the reason behind that is logical. [00:50:14] Speaker 00: It's the exact same claim. [00:50:17] Speaker 00: I would refer the court, if you're looking for some guidance on this issue, to Hensel Phelps versus Thompson Masonry, a case from November of 2016 where Hensel Phelps attempted to make the same type of argument to the Virginia Supreme Court. [00:50:30] Speaker 00: And they said, you can't re-characterize an indemnity provision or a breach of contract claim as an indemnity provision. [00:50:37] Speaker 00: But if the court were to reach the indemnity provision as a third party claim, it should affirm the district court's proper application. [00:50:44] Speaker 01: I want to make sure I understand your argument on this. [00:50:47] Speaker 01: the argument that Hensel Phelps did not appeal the determination. [00:50:56] Speaker 01: Which is it that you're saying they did not appeal? [00:50:59] Speaker 00: Hensel, in the initial motion to dismiss or alternatively motion for summary judgment, we move to dismiss the indemnity claim on two separate grounds. [00:51:11] Speaker 00: First, because the indemnity provision did not apply to third party claims, which is the issue, or first party claims, which is what they did appeal. [00:51:18] Speaker 00: Right. [00:51:18] Speaker 00: And second, because the indemnity claim, like the breach of contract claim, was barred by the applicable statute of limitations. [00:51:25] Speaker 01: Now, the problem there, is it clear whether the district judge ever ruled on that issue? [00:51:30] Speaker 00: I believe that it is. [00:51:31] Speaker 00: The district court's memoranda opinion specifically says that he identifies in footnote one that the only two issues that were not reached related to two different theories of no damages being played. [00:51:43] Speaker 01: But so then your position is necessarily reached the other issue, but he never said anything about it. [00:51:52] Speaker 00: Your honor, the district court entered an order granting the motion for summary judgment and the only carve out of that grant was the two issues that were not reached. [00:52:04] Speaker 01: So you think necessarily he had to rule in favor of that which he did not carve out. [00:52:10] Speaker 00: Well, and I believe, actually, the opinion itself did expressly carve it out, as Judge Leon explained. [00:52:16] Speaker 00: You mean carve it out? [00:52:18] Speaker 00: Sorry, that Judge Leon expressly addressed it. [00:52:21] Speaker 00: In the opinion, Judge Leon articulated our motion as follows. [00:52:27] Speaker 00: Cooper Carey argues, inter alia, that Hensel Phelps's claims, plural, are time barred, and as to the claim, singular, based on the indemnification clause, [00:52:38] Speaker 00: Cooper Carey moves for the additional reason that the agreement plainly does not apply to this factual situation. [00:52:46] Speaker 00: So in the outset when he's framing his opinion, he identifies there are claims, plural, that we have moved on timeliness grounds. [00:52:54] Speaker 00: and that there's an additional ground for the indemnity provision. [00:52:57] Speaker 00: And the analysis, if you look at his analysis, is much akin to the question that you asked earlier, is that really there is no distinction in Hensel Phelps's mind between the two types of claims. [00:53:10] Speaker 00: So the analysis is the same. [00:53:12] Speaker 00: And that issue was not appealed. [00:53:15] Speaker 00: Hensel Phelps does not contend that they appealed the issue. [00:53:18] Speaker 00: And so therefore we don't believe that the second issue on appeal need be reached by this Court. [00:53:23] Speaker 00: Let's assume it is reached. [00:53:25] Speaker 00: If it is reached, we believe that this Court should apply the same canons of contractual construction. [00:53:30] Speaker 00: that the district court applied to correctly conclude that it only applies to third party claims and not first party claims. [00:53:37] Speaker 00: The first rule of contractual construction we believe must be applied is the whole agreement rule. [00:53:43] Speaker 00: That is, contracts should be interpreted to give meaning to all of the provisions in the contract. [00:53:48] Speaker 00: Here, the indemnity provision includes two duties, a duty to indemnify and a duty to defend, conjunctively. [00:53:57] Speaker 00: And the duty to indemnify and the duty to defend all relate to the same defined categories of claims, capital C claims, which include any claim, judgment, lawsuit, damage, liability, and costs and expenses. [00:54:13] Speaker 00: So that's capital C claims, and you must be able to both indemnify and defend against those claims. [00:54:21] Speaker 01: It makes no sense to defend against your claim against yourself. [00:54:24] Speaker 00: Absolutely. [00:54:25] Speaker 00: It's an impossibility. [00:54:26] Speaker 00: So the only way to read it is as a third party indemnity to give meaning to the defend obligation, which Hensel Phelps deprives of meaning in its entirety. [00:54:36] Speaker 00: The other provision I would refer the court to is further down in Article 6.1, the indemnity provision, which discusses that in the event that any such capital C claims are made, asserted, or threatened against any indemnities here under, there are a variety of self-help remedies available to the indemnities. [00:54:56] Speaker 00: Elsewhere in the design agreement, specifically Article 4.06 on page 25 of the Joint Appendix, there are the self-help remedies that Hensel-Felps has in the event of a first-party claim. [00:55:08] Speaker 04: So what do you make of all these other provisions that talk about anticipating a reasonable number and variety of revisions in the services under the contract, that the parties are gonna work together to develop value engineering suggestions, adjustments in the scope. [00:55:26] Speaker 04: There's all these sort of open-ended [00:55:29] Speaker 04: undertakings to work together. [00:55:31] Speaker 04: So your view is basically you have a first time that your counterparty falls short of the standard of care in the contract or of the obligations of the contract. [00:55:42] Speaker 04: You file a lawsuit within three years of that, even if the contract's ongoing, and you kind of add claims to your [00:55:50] Speaker 04: or you told it or whatever, you kind of add to the litigation file as you go along, and then at the end of the day, you go back through that with your lawyers and you say, well, actually that got dealt with, that got dealt with, that got dealt with, and these two didn't, and then you proceed with the litigation? [00:56:05] Speaker 00: uh... respectfully that's what dc law is is that you file within three years from the first breach and the difference between the construct and i i thought it wasn't clear before the difference between construction contract claims and and reading judge leon's opinion there was this repeated emphasis that he even held that unitary contracts means something [00:56:27] Speaker 00: The word that kept getting omitted from Judge Leon's opinion is the word construction contract. [00:56:32] Speaker 00: And there's a difference between construction contracts and design agreements, which has been recognized. [00:56:36] Speaker 00: And that is that in a construction contract, a contractor has the ability to correct defective work until such time as they are scheduled to deliver the work without being in breach. [00:56:50] Speaker 00: A wall when it's getting built is not in conformity with the entire requirements of the contract until it is completed. [00:56:57] Speaker 00: The design documents, however, cannot be cured after they've been put into the field to avoid damages. [00:57:05] Speaker 00: Hensel Phelps's position, in essence, is that while there are provisions that require correction of deficiencies and performance of that, that Cooper-Carrie did not have the ability to revise the preliminary design documents. [00:57:23] Speaker 00: to avoid subsequent damages to the tune of 8.5 million dollars, whereas the construction contractor cases that are at issue, the contractor has until the substantial completion of the project to remedy any deficiencies. [00:57:36] Speaker 00: One of them you're dealing with designs that are put into the field, and once they're put into the field, they can only be revised after there's a problem that gets discovered. [00:57:45] Speaker 04: Not necessarily. [00:57:47] Speaker 04: I mean, it seems like you could do something that, you know, the design was wrong, and you could make it good. [00:57:54] Speaker 04: Workarounds happen all the time, right? [00:57:57] Speaker 00: In this particular situation, Hensel Phelps couldn't find a workaround that cost less than $5.5 million, and their position is that they had to carry that $5.5 million and that the D.C. [00:58:08] Speaker 00: law, D.C. [00:58:09] Speaker 00: statute of limitations, did not afford them a remedy for that $5.5 million. [00:58:14] Speaker 00: until the substantial completion of the project, which doesn't make sense at all. [00:58:21] Speaker 00: Does that address that issue? [00:58:24] Speaker 04: I think so. [00:58:25] Speaker 04: Thank you. [00:58:27] Speaker 00: The indemnity provision also relates to, and I'm sticking with the whole agreement rule here, the claims must be capable of being made, asserted, or threatened against the indemnities. [00:58:40] Speaker 00: And obviously, Hensel-Felts cannot make, assert, or threaten claims against itself. [00:58:45] Speaker 00: So in order to give meaning to that language in the indemnity provision itself, you have to construe that as a third-party indemnity. [00:58:52] Speaker 00: We also believe that the canon of the plain meaning rule applies here. [00:58:58] Speaker 00: That is, of course, where the language has a generally prevailing meaning. [00:59:01] Speaker 00: It is to be interpreted in accordance with that meaning. [00:59:04] Speaker 00: And here, indemnity does have a generally recognized meaning as applicable to third party claims. [00:59:09] Speaker 00: That's what the landmark decision court held when they cited to CJS saying, an indemnity provision generally does not apply to claims between the parties to the agreement [00:59:19] Speaker 00: but obligates the indemnitor to protect the indemnity against claims brought by third parties. [00:59:25] Speaker 00: And that's not just the general understanding writ large in the law, but it's specific to the construction industry. [00:59:32] Speaker 00: The leading construction law treatise cited extensively by Hensel-Felfs throughout its briefs thought so little of the concept of first-party indemnity provisions, that this is what they described [00:59:46] Speaker 00: Once in a while, an indemnity will become particularly inventive and attempt to claim that the indemnitor's obligation to indemnify it against, quote, all claims includes the indemnitor's own claims against the indemnity. [01:00:03] Speaker 00: the leading construction law treatise recognizes that in the construction industry the argument that all claims covers first party claims is a particularly inventive argument and that's what we have here is a particularly inventive argument. [01:00:20] Speaker 00: Accordingly, we believe the only way to give meaning to all of the words in the indemnity provision, as well as the rest of the design agreement itself, is to construe it as applicable to third-party claims, not first-party claims. [01:00:33] Speaker 00: And therefore, we ask the court affirm district court's ruling. [01:00:37] Speaker 02: All right. [01:00:37] Speaker 02: Thank you, Mr. Shoemaker. [01:00:40] Speaker 02: Ms. [01:00:41] Speaker 02: Stetson had no time left. [01:00:43] Speaker 02: We'll give you two minutes of rebuttal time. [01:00:45] Speaker 03: Thank you. [01:00:45] Speaker 03: I appreciate that Judge Brown. [01:00:47] Speaker 03: A few quick points. [01:00:48] Speaker 03: The first is with respect to DC law, the case that Mr. Shoemaker did not identify that actually contains the statement of DC law [01:00:57] Speaker 03: is Aaron Haft versus Price. [01:00:59] Speaker 03: It's the case we cited in our opening and reply briefs, 483, a second, 1192. [01:01:03] Speaker 03: This is the case that says a breach arises from the date of completion. [01:01:09] Speaker 03: The statute of limitations begins to run when a contract is complete. [01:01:13] Speaker 03: The capital place case, of course, involves the discovery rule, which only comes into play if there's [01:01:19] Speaker 03: a latent defect after the contract is complete. [01:01:23] Speaker 03: Ehrenhaft versus Price is the DC rule. [01:01:26] Speaker 03: That is the rule that we're asking to be applied here. [01:01:29] Speaker 03: It is also the rule that applies no matter whether the contract is labeled a construction agreement or a design services agreement. [01:01:39] Speaker 03: You can imagine a divisible construction contract. [01:01:42] Speaker 03: You can imagine [01:01:43] Speaker 03: as in this case, a unitary design services contract. [01:01:47] Speaker 03: The thing that you look at isn't what it's called. [01:01:49] Speaker 03: You look at what it contains. [01:01:51] Speaker 03: And if the contract contains provision for a full course of performance through completion and construction of the project payable by a lump sum, it's a unitary contract. [01:02:02] Speaker 03: That is this case, and that means that the statute of limitations did not begin to run until April of 2014. [01:02:08] Speaker 03: On the indemnity issue, [01:02:14] Speaker 03: First of all, rather than define from what Judge Leon didn't say an intention to rule on something, I suggest we look at what he did say. [01:02:24] Speaker 03: With respect to the indemnity, what he says at Joint Appendix 370, I have concluded that H.P. [01:02:31] Speaker 03: Hensel Phelps's claims based on design errors are time barred. [01:02:34] Speaker 03: And the indemnification clause refers only to Hensel Phelps's prospective liabilities in third-party litigation. [01:02:42] Speaker 03: That's Joint Appendix 370, Joint Appendix 378, Hensel Phelps's time barred from bringing its breach claim. [01:02:49] Speaker 03: Joint Appendix 380. [01:02:50] Speaker 03: Reading the indemnification clause in the most obvious way, it requires Cooper Carey to cover Hensel Phelps's liabilities when and if a third party sues [01:03:00] Speaker 03: over problems caused by Cooper Carey's fault, which, by the way, Mr. Shoemaker is not defending. [01:03:06] Speaker 03: Nowhere in those holdings, not the statement of Cooper Carey's argument, not the footnote pertaining to an entirely separate argument, nowhere in those holdings did Judge Leon ever say, oh, and by the way, the indemnity claims are time barred also. [01:03:22] Speaker 03: The reason is that he couldn't. [01:03:24] Speaker 03: The indemnity claims arise from when the expense is incurred. [01:03:29] Speaker 03: And if you look at the claim narrative, and you look at the many, many exhibits to the claim narrative, containing the many payments made to the many third-party contractors that Hensel-Feldts had to compensate, what you will see is that all of those payments were made circa 2013 and 2014. [01:03:45] Speaker 03: That's why that claim wasn't in time. [01:03:47] Speaker 01: That's the first time you've embraced the claim narrative. [01:03:51] Speaker 03: I don't think it's the first, but certainly with respect to rebutting the argument that there was some holding that didn't exist, I'm very happy to embrace the claim there. [01:04:01] Speaker 03: With respect to this idea that the indemnification clause is referenced to duty to defend, [01:04:07] Speaker 03: somehow shrinks the rest of those words to apply only to third party claims, the duty to defend and the duty to indemnify are two different things. [01:04:16] Speaker 03: They come up in two different contexts all the time. [01:04:19] Speaker 03: You don't defend against a claim for an expense that a cement company submits to you, you pay it. [01:04:25] Speaker 03: You don't defend it just because it's not litigation. [01:04:27] Speaker 03: It doesn't mean that somehow [01:04:28] Speaker 03: This indemnity clause only applies to that. [01:04:32] Speaker 03: So too with this idea that where there's a claim, made, threatened, or asserted. [01:04:36] Speaker 03: What that sentence actually says is, if any such claims are made, threatened, or asserted, then you have to make certain provision for that. [01:04:45] Speaker 03: That means in the context of a third party expense submission, certain things have to be followed. [01:04:51] Speaker 03: But that doesn't rule out the possibility of a first party expense. [01:04:55] Speaker 03: And all of this dialogue. [01:04:57] Speaker 03: about what that indemnification clause does and does not cover obscures the fact that Mr. Shoemaker apparently concedes that over seven million dollars of the eight and a half million dollars, or maybe the whole nut, actually is a third party expense. [01:05:16] Speaker 03: That is our argument. [01:05:17] Speaker 03: He didn't refute it. [01:05:18] Speaker 03: We think it should be reversed on that alone and sent back. [01:05:21] Speaker 02: All right. [01:05:22] Speaker 03: Thank you. [01:05:23] Speaker 02: The case will be submitted.