[00:00:00] Speaker 00: Case number 20-1212, Delaware Division of the Public Advocate et al. [00:00:05] Speaker 00: Petitioners versus Federal Energy Regulatory Commission. [00:00:09] Speaker 00: Ms. [00:00:09] Speaker 00: Roberts for the petitioners, Ms. [00:00:11] Speaker 00: Benta for the respondent, Mr. Flynn for the intervener. [00:00:16] Speaker 01: Morning, council. [00:00:17] Speaker 01: Ms. [00:00:17] Speaker 01: Roberts, please proceed when you're ready. [00:00:19] Speaker 03: Good morning. [00:00:19] Speaker 03: Thank you. [00:00:20] Speaker 03: May it please the court, my name is Casey Roberts appearing on behalf of petitioners. [00:00:25] Speaker 03: This case is about the Federal Energy Regulatory Commission failing to do its job of protecting consumers from paying excessive rates for electric generating capacity. [00:00:34] Speaker 03: For years, PJM's capacity auction has forced consumers to pay prices higher than necessary to attract sufficient investment in capacity and also to buy far more capacity [00:00:45] Speaker 03: than needed to meet the reliability standard. [00:00:48] Speaker 03: When given a chance in this case to set a course that would alleviate those unnecessary costs, the commission instead approved a demand curve that will result in nearly $100 million in excess costs each year. [00:01:03] Speaker 03: Petitioners assert three errors in the commission's orders. [00:01:06] Speaker 03: First, approval of the Greenfield combustion turbine as the reference resource, [00:01:11] Speaker 03: Second, approval of blanket application of the 10% adder in modeling energy revenues of the combustion turbine, which further increased the amount consumers would need to pay for capacity. [00:01:23] Speaker 03: And third, the Commission's decision that it need not consider oversupply in determining whether the filed demand curve would result in reasonable rates. [00:01:32] Speaker 03: First, FERC aired an approving PJM's decision to use the Greenfield Combustion Turbine as the reference resource. [00:01:38] Speaker 03: The Greenfield Combustion Turbine is not an accurate representation of the cost of building new capacity in the PJM region. [00:01:46] Speaker 03: The record shows that cost is estimated to be 25 to 63% lower than the cost of building the new Greenfield combustion turbine. [00:01:53] Speaker 03: A demand curve based on a combustion turbine will, in the estimation of PJM's own consultant, perpetuate PJM's chronic excess capacity at a cost to consumers. [00:02:06] Speaker 03: Commission's approval of PJM's choice of reference technology does not hold up under the three-part test that FERC has applied in two recent ISNU England orders to the same question. [00:02:18] Speaker 03: Under that test, FERC considers whether the proposed reference resource is likely to be built, whether its costs and revenues can be estimated accurately, and whether a curve based on that resource will procure enough capacity to meet the reliability standard, but not so much that consumers pay unnecessary costs. [00:02:38] Speaker 03: There's no evidence that a greenfield combustion turbine is likely to be built in PJM. [00:02:42] Speaker 03: None have been built since 2014, a time period in which roughly 27,000 megawatts of new combined cycle capacity has cleared the auction. [00:02:54] Speaker 03: FERC points to two brownfield combustion turbines that have been developed since 2014, but the construction of these cheaper facilities at existing sites does not show that a more expensive greenfield combustion turbine is likely to be built in the future. [00:03:09] Speaker 03: FERC leans heavily on theoretical advantages of combustion turbines, such as lower total cost and quick deployment. [00:03:17] Speaker 03: But these theoretical benefits are belied by the decisions that developers of new generation have made over and over again in recent years. [00:03:25] Speaker 03: Likely to be built must mean more than theoretically possible somebody could want to build it. [00:03:31] Speaker 03: For the demand curve to reasonably approximate the cost of new entry, as FERC has repeatedly held is critical to this type of inquiry. [00:03:39] Speaker 01: Can I ask you, Mr. Roberts, it seemed like part of the commission's rationale on this score had to do with the reliability and the reliability of the alternate baseline that you would propose. [00:03:51] Speaker 01: What's your response to that? [00:03:52] Speaker 01: Because that seems like certainly a reasonable consideration to take into account. [00:03:58] Speaker 03: Yeah, so the commission did sort of repeat PJM's assertion that there were misestimation risks associated with using a combined cycle resource as the reference resource that could result, I think they said, in specific reliability risks. [00:04:13] Speaker 03: However, what FERC was citing to there was PJM's sort of cherry picking of certain evidence from the record. [00:04:20] Speaker 03: We provided and pointed to evidence in the record that other curves based on the combined cycle resource would, in fact, [00:04:26] Speaker 03: meet reliability, even accounting for some risk of misestimating the net cost of new entry. [00:04:33] Speaker 03: And FERC never addressed that evidence that we pointed to, which undermines the conclusion that it reached. [00:04:37] Speaker 03: And that's not reason decision-making. [00:04:40] Speaker 02: But I thought at least in the Brattle report that Brattle had a number of different models. [00:04:46] Speaker 02: Are we talking about the combined cycle curves? [00:04:49] Speaker 02: And that the other curves also had some issues in terms of reliability. [00:04:54] Speaker 02: They didn't necessarily perform [00:04:56] Speaker 02: better or meet the target? [00:05:00] Speaker 02: There was one I thought that maybe did, but most of them had issues as well. [00:05:05] Speaker 03: Yeah, so Bridal evaluated two curves based on the combustion turbine and four curves based on the combined cycle, and then each of those had sort of other parameters being adjusted. [00:05:14] Speaker 03: And two of the four combined cycle-based curves that it evaluated would meet the reliability standard of [00:05:22] Speaker 03: no more than one in 10 outages on average, or sorry, one outage in 10 years on average. [00:05:29] Speaker 03: And both of those curves, that was curves C and D, met that reliability standard, even if their net cost of new entry was underestimated by 20%. [00:05:39] Speaker 02: But the C curve, it performed okay in terms of reliability, but it was still short of the curve that PJM preferred and that FERC approved, right? [00:05:50] Speaker 02: which was the B curve, the combustion turbine based curve. [00:05:54] Speaker 03: Yeah, that's correct. [00:05:55] Speaker 03: Curve C and curve D, which are the two that met the reliability standard were not, I guess you could say quite as reliable as the B curve. [00:06:04] Speaker 03: However, both of them exceeded the reliability standard that FERC has set out in these cases. [00:06:09] Speaker 03: They both have less than the one outage in 10 years. [00:06:14] Speaker 03: And so, [00:06:16] Speaker 03: we contend that these curves exceed the standard and FERC hasn't justified why consumers should be required to pay costs above what is needed to meet the reliability standard. [00:06:32] Speaker 02: And isn't it the case that the C curve was also one of the ones that didn't eliminate that rightward shift that everybody seemed to want to get rid of? [00:06:38] Speaker 02: That's correct. [00:06:40] Speaker 02: So we're talking here more like [00:06:43] Speaker 02: a quarter of a million rather than the 100 million that your briefing focuses on, that the difference between the B curve and the C curve is much smaller. [00:06:54] Speaker 03: Yeah, that's correct. [00:06:55] Speaker 03: I can't remember exactly what the savings were, but what you suggest sounds about right. [00:06:59] Speaker 03: So yeah, the savings increase from the C curve down through the F curve. [00:07:06] Speaker 03: But I'm sorry, I think I... [00:07:12] Speaker 03: I forgot your question relating to that. [00:07:15] Speaker 02: No, just that it's a narrower perceived benefit in terms of potential cost and forgoes some other benefits to consumers to go with the CC curve, the alternative. [00:07:35] Speaker 02: So sure. [00:07:37] Speaker 02: Yeah, I understand the factual coordinates, but it's really an observation more than more than a question. [00:07:43] Speaker 03: Okay. [00:07:44] Speaker 03: Okay. [00:07:44] Speaker 03: Thank you. [00:07:44] Speaker 03: I would I would just add that, you know, should if the commission were have to decide. [00:07:50] Speaker 03: were to have decided that a curve based on a combustion turbine was not just unreasonable, then I would expect, you know, PJM to have reconsidered and maybe like looked at more candidate curves based on a combined cycle to sort of test different options and combinations of parameters. [00:08:09] Speaker 03: All right. [00:08:11] Speaker 03: There's no evidence that a Greenfield combustion turbine is likely to be built in PJM. [00:08:17] Speaker 03: Excuse me, sorry. [00:08:18] Speaker 03: So NextFIRC failed to respond to evidence that the costs and revenues of the combustion turbine cannot be determined with confidence, the second factor in the ISA New England test. [00:08:28] Speaker 03: PJM's filing shows that there is inadequate market data to estimate the future revenues of combustion turbines. [00:08:35] Speaker 03: Petitioners pointed to this evidence, both in our protest and on re-hearing, but FERC's orders did not address this evidence, which is squarely on point. [00:08:44] Speaker 03: Instead, FERC focused on why it might be hard to accurately estimate the revenues for a technology that PJM did not propose to use, the combined cycle gas plants. [00:08:54] Speaker 03: But there again, FERC fails to address evidence contradicting its position. [00:08:59] Speaker 03: PJM's own consultants specifically disagreed with the conventional wisdom that combined cycle resources are subject to more estimation error. [00:09:08] Speaker 03: Petitioners pointed FERC to this other evidence in our request for hearing, but FERC failed to respond. [00:09:13] Speaker 03: This does not constitute reason decision-making as required by the APA. [00:09:19] Speaker 02: Well, so the logic, though, is that it's harder to estimate the revenues from combined cycle because more of them rely on the real time energy markets, right, the day ahead and the real time energy markets, which have yet to occur. [00:09:34] Speaker 02: Those are going to occur years hence. [00:09:36] Speaker 02: So it seems intuitively accurate, especially when we're talking about capacity markets, which are [00:09:47] Speaker 02: insurance against exceptional energy market conditions. [00:09:51] Speaker 02: So everything's going to be haywire by the time the capacity that's being auctioned today is in use. [00:10:02] Speaker 02: So maybe the energy markets are going to be more volatile in that context. [00:10:07] Speaker 02: And any technology or any reference resource that is more reliant on those energy markets [00:10:15] Speaker 02: you know, for the net, for the cone, kind of by just the logic of the situation is going to be more harder to estimate, harder to pin down. [00:10:27] Speaker 02: No? [00:10:28] Speaker 03: Well, so what I would say is that the amount that developers are willing to offer into the capacity auction out reflects their anticipation of what energy revenues they will earn. [00:10:41] Speaker 03: And the bridle said that that was very, very hard to predict for combustion turbines, right. [00:10:47] Speaker 03: And even though PJM and FERC both state that, oh, well combined cycles are more reliant on energy revenues. [00:10:54] Speaker 03: Basically any error is very consequential. [00:10:58] Speaker 03: In fact, the record shows and PJM pointed to this in its transmittal letter that combined cycles rely on energy market for 61% of their revenues, but combustion turbines rely on it for 27%, which is only half as much. [00:11:15] Speaker 03: And so this is where FERC really failed to engage in reason decision-making when looking at, if the consultant is telling you it's very hard to develop accurate [00:11:24] Speaker 03: energy revenue forecast for combustion turbines, it's quite easy to do it for combined cycles. [00:11:32] Speaker 03: That it doesn't follow that will combine cycles, therefore, you cannot estimate their their neck hone with accuracy because the difference between the extent to which they rely on those energy revenues is really not quite as stark as PJM presented. [00:11:53] Speaker 03: Commission did not address the third and most important factor in the ISA New England test, whether PJM's choice of reference technology would result in unnecessary costs for consumers. [00:12:04] Speaker 03: Failure to examine a central issue presented, especially one that ties so closely to the commission's core duty to ensure just and reasonable rates, renders its decision arbitrary and capricious. [00:12:16] Speaker 03: In its brief before this court, FERC has no answer for this oversight. [00:12:20] Speaker 03: The record shows that selecting a combustion turbine as the reference resource would lead to higher prices and more capacity than needed to ensure reliability compared to another curve based on the combined cycle reference resource, which we were discussing a minute ago. [00:12:34] Speaker 03: Petitioners twice pointed FERC to this evidence, but the commission does not respond to either of the evidence or petitioners argument. [00:12:43] Speaker 03: So I'm going to go ahead and if there are no further questions at this time, save the remainder of my time for rebuttal. [00:12:50] Speaker 02: Let me just ask you, you open talking about ISO New England, but has FERC treated that as a sort of generally applicable test? [00:13:00] Speaker 02: I'm not aware of it applying that particular analysis other than to ISO New England. [00:13:07] Speaker 03: Yeah, FERC has not expressly applied that test to PJM. [00:13:12] Speaker 03: The test was developed first in the 2014 order and in ISA New England and then reaffirmed in a 2017 order. [00:13:20] Speaker 03: However, the question that's being evaluated by FERC in those ISA New England cases is identical to what's being [00:13:26] Speaker 03: evaluated in these PJM cases and you know like cases should be treated similarly without an adequate explanation for differentiating among them and so we see no reason why the ISA New England test and those three criteria should not apply to the exact same question when evaluated in the PJM context. [00:13:45] Speaker 02: You also emphasized repeatedly that [00:13:50] Speaker 02: PJM used a greenfield combined turbine facility rather than a brownfield one to calculate the costs. [00:13:57] Speaker 02: But the site isn't really part of the definition. [00:14:00] Speaker 02: The site affects the net cone, but not the reference resource. [00:14:06] Speaker 02: And that seems like that would require a distinct challenge. [00:14:09] Speaker 02: You've challenged the choice of reference resource. [00:14:13] Speaker 02: So I just wonder whether the site which affects the net [00:14:20] Speaker 02: Cone is actually in this petition. [00:14:25] Speaker 02: Is that properly before us? [00:14:27] Speaker 03: Yeah, I understand. [00:14:29] Speaker 03: So the reason that we focused on the fact that FERC approved a Greenfield combustion turbine is that the costs of that combustion turbine are more than those at a Brownfield site, right? [00:14:40] Speaker 03: So there's a cost of gas and electric interconnection, there's cost of buying land, and those additional costs take it even further away from what we see is the actual cost of new entry. [00:14:50] Speaker 03: in the region, which over the past, you know, I guess five or so years has been 50 to 80% lower than what PJMs administrative net cone had been. [00:15:00] Speaker 03: And so that takes you even further away from the benchmark that FERC itself has set out in these cases that this administrative net cone value is supposed to accurately represent the true cost of net entry of new entry in the region. [00:15:16] Speaker 01: Okay. [00:15:17] Speaker 01: Unless my colleagues have additional questions for you at this time, we'll hear from the commission and interviewer. [00:15:21] Speaker 01: Thank you, Ms. [00:15:22] Speaker 01: Roberts. [00:15:23] Speaker 01: Spanta. [00:15:25] Speaker 04: Good morning. [00:15:25] Speaker 04: I'm Carol Banta for the commission. [00:15:27] Speaker 04: And I'll begin with this last discussion of the New England cases. [00:15:33] Speaker 04: In particular, looking at the 2014 case, one thing to remember about those cases is that New England, like PJM, has [00:15:42] Speaker 04: the commission said the tariff does not prescribe how they need to select this resource. [00:15:47] Speaker 04: And so New England came in and said, here are the factors that we considered. [00:15:53] Speaker 04: And then in the paragraphs that the petitioners have cited, the commission said, yes, your analysis makes sense to us. [00:16:00] Speaker 04: Now to be clear, New England came in under section 205 with its own proposal to which the commission has what this court has called a passive and reactive role. [00:16:10] Speaker 04: So in PJM, which also has no prescription in its tariff for how to make this decision, PJM came in with its own discussion of here's what we propose, here are our reasons for it. [00:16:23] Speaker 04: So the commission said, sure, we'll look at the New England factors because they are similar considerations and they are accounted for in this case. [00:16:30] Speaker 04: But as far as the question of whether that's some kind of binding precedent, there's nothing in the New England cases where the commission purports to set forth a test [00:16:39] Speaker 04: that it will apply broadly to every system operator. [00:16:43] Speaker 04: And indeed it was echoing New England's own section 205 filing, which the New England operator was within its statutory rights to make. [00:16:52] Speaker 04: And the commission was considering that proposal. [00:16:56] Speaker 04: In this case, the commission is considering PJM's proposal and whether PJM adequately supported its case. [00:17:04] Speaker 04: Now I want to point to where the commission started its analysis in the very beginning of its substantive discussion in the curve order, which begins at paragraph 16. [00:17:15] Speaker 04: I begin with cost to consumers because that's what the commission in fact did. [00:17:19] Speaker 04: The commission started its analysis in paragraph 16 and it echoes it again in paragraph 20, which is the first argument that it considers in this case, [00:17:29] Speaker 04: With the focus on cost to consumers and the language in paragraph 16 on JA 298 is in the second sentence. [00:17:36] Speaker 04: We find PJM's proposed changes result in a curve that meets PJM's reliability needs at a reasonable total cost to load. [00:17:44] Speaker 04: Load means end users. [00:17:46] Speaker 04: It means consumers. [00:17:48] Speaker 04: And I'd point out that reliability needs are not merely a concern of cost to suppliers. [00:17:52] Speaker 04: Reliability is a consumer interest as well. [00:17:55] Speaker 04: And one of the commissions [00:17:57] Speaker 04: primary statutory responsibilities under the federal power act, in addition, of course, to just and reasonable costs. [00:18:07] Speaker 04: And what this court has held many times, including in particular in advanced energy, is that there is a balance that sometimes in advanced energy, providing reliability under PJAM's 205 proposal in that case, was going to cost more. [00:18:24] Speaker 04: And it was a balance of reliability [00:18:27] Speaker 04: versus perhaps costing more, is that adjustment reasonable cost? [00:18:32] Speaker 04: And this court said in advanced energy that the commission in approving PJM's proposal had made that balance and had shown that balance. [00:18:45] Speaker 04: So looking at paragraph 16, the commission starts by saying we find this reasonably balances reliability and cost. [00:18:53] Speaker 04: Then we look at paragraph 17 where it's summarizing [00:18:57] Speaker 04: at the beginning of PJM's case for its proposal, there's no dispute in this case that PJM's proposed changes lowered the prices of capacity. [00:19:07] Speaker 04: It lowered the costs. [00:19:08] Speaker 04: It not only did the shift to the left or undid, I should say it undid an escalation of prices that had been put in place in the previous, I believe 2014. [00:19:18] Speaker 04: It undid that 1% shift to the right by shifting to the left. [00:19:23] Speaker 04: That alone brings the curve down. [00:19:25] Speaker 04: Also the changes that made all but one of which or most, I should say all but two of which in this case are not contested on appeal brought that straight line. [00:19:37] Speaker 04: If you look at the commission's brief at page 13 has the old, the previous curve and the revised curve, it brought that flat line down before the curve even begins its descent at the target margin. [00:19:52] Speaker 04: That's things like using the H class [00:19:55] Speaker 04: turbine instead of F class turbines, that was highly contested below. [00:19:59] Speaker 04: That's not before the court on appeal, but that made a big difference in cost. [00:20:04] Speaker 04: The other changes to labor costs, cost of capital, various things, all these other changes, there's no dispute that they brought the cost down. [00:20:12] Speaker 04: So petitioners argument here is that the cost should be even lower and that PGM is being too conservative about reliability. [00:20:21] Speaker 04: So that's the balance that was in front of the commission. [00:20:25] Speaker 04: that's also on the 205 proposal from PJM and it's also before this court. [00:20:30] Speaker 04: So then in paragraphs 18 to 19, the commission lays out the public interest entities argument that the existing curve has been producing over supply. [00:20:40] Speaker 04: And in paragraph 20, it again echoes the language about reasonable cost to load because it says PJM's analysis in its 205 filing is sufficient to meet the requirements of its tariff [00:20:53] Speaker 04: which is designed to ensure that the proposed VRR curve meets BGM's reliability needs at a reasonable cost load. [00:21:01] Speaker 04: And what's important about paragraph 20, when it says the requirements of the tariff are designed to ensure this, we're talking about the larger capacity market mechanism, which is not presented in this case, either to the commission or to the court. [00:21:15] Speaker 04: The capacity market mechanism is previously approved, most recently in advanced energy. [00:21:21] Speaker 04: And this is just the inputs to one part of it. [00:21:23] Speaker 04: And the commission says that PJM has supported the changes it wants to make to the inputs to this one aspect of the market mechanism. [00:21:33] Speaker 04: So if the problem, if the assertive problem here is that the market mechanism is resulting in a chronic oversupply, the answer to that is to bring a challenge under 206 to the market. [00:21:47] Speaker 04: to the larger market mechanism that's previously approved that's not an issue in this case. [00:21:53] Speaker 04: What was before the commission in this case is did PJM adequately support with evidence and its own explanation the changes that it wanted to make to the inputs and its reasons for making them and why those are reasonable. [00:22:09] Speaker 04: It didn't have to exclude every other possible method, although PJM did go ahead and explain why it wasn't. [00:22:17] Speaker 04: changing to the combined cycle. [00:22:18] Speaker 04: And the commission considered PJM's points in that regard. [00:22:22] Speaker 02: Ms. [00:22:22] Speaker 02: Banta, can you talk about the 10% adder? [00:22:25] Speaker 02: And I don't know. [00:22:27] Speaker 02: I did not see in the record. [00:22:29] Speaker 02: I think the Brattle report said it was mixed and inconclusive. [00:22:33] Speaker 02: But do you know how often in practice the combustion turbine [00:22:42] Speaker 02: offers into the energy market actually use the 10% permission, the 10% adder because it just struck me that just because it's authorized wouldn't necessarily just as a sort of a logical matter wouldn't necessarily support including it as if every [00:23:03] Speaker 02: generator used it. [00:23:06] Speaker 02: Maybe 20% of them use it, in which case maybe it should be a weighted portion of the 10%. [00:23:12] Speaker 02: So it was curious to me that I didn't see any information about something that I gather is optional with the generator, how frequently it's actually used. [00:23:28] Speaker 02: Because I gather the whole inquiry here is accuracy when we're talking about [00:23:32] Speaker 02: trying to calculate the net cone and do that in terms of subtracting revenues? [00:23:42] Speaker 04: I think the only data we have in the record is Brattle saying, we just don't know. [00:23:48] Speaker 04: Some companies use it and some don't. [00:23:53] Speaker 04: Mixed reactions on JA 146 was exactly what Brattle said. [00:23:57] Speaker 04: Yeah. [00:23:57] Speaker 04: And so in trying to determine the price of a hypothetical resource, the reference resources is a hypothetical resource with the costs that we know. [00:24:09] Speaker 04: I think what the commission said is given that, I think as the commission says, the offset calculated or estimated for the energy and ancillary services offset. [00:24:25] Speaker 04: reflects all eligible offer cost components. [00:24:29] Speaker 04: And so the commission just made the judgment that because the 10% is provided in the tariff and was previously in a different case, not at issue here, determined to be just and reasonable, we don't see a reason to exclude a component that the tariff permits. [00:24:48] Speaker 02: It seems perverse though. [00:24:49] Speaker 02: I mean, just because it's permitted. [00:24:52] Speaker 02: doesn't mean it's used. [00:24:53] Speaker 02: And if the inquiry or if the project, you know, once we're looking at trying to accurately assess Cohen is accuracy, it seems like it's an unnecessary distortion. [00:25:05] Speaker 02: I mean, unless that information is just not obtainable, then what I would want to know is, you know, what is the experience of combustion turbines [00:25:17] Speaker 02: in the energy market, how frequently do they take advantage of the allowable 10% and how frequently do they say, no, I'm not gonna do that because of first lease cost dispatch. [00:25:30] Speaker 02: I'm not gonna take advantage of the allowable 10% because that's just gonna put me to the back of the line. [00:25:35] Speaker 02: I'm not gonna be able to sell the energy I have. [00:25:37] Speaker 02: So is that something, is that information that's not available to the commission? [00:25:40] Speaker 02: Not for some reason wouldn't be, [00:25:45] Speaker 02: accurately predictive. [00:25:47] Speaker 02: Why isn't that information obtainable? [00:25:49] Speaker 02: I thought Brattle, in fact, gave a nod to maybe you should get that information. [00:25:53] Speaker 02: Right. [00:25:54] Speaker 04: And I think Mr. Flynn might be able to answer some of that. [00:25:58] Speaker 04: I know PJM argued in its brief that it would be difficult to model. [00:26:01] Speaker 04: One thing I would point out, the hypothetical reference resource is chosen for the entire region. [00:26:07] Speaker 04: The curve is done a little differently and the markets are run differently [00:26:14] Speaker 04: in some of the sub regions. [00:26:16] Speaker 04: And I do believe that there are some parts of the PJM region where, for instance, access to gas supplies is different than in other parts. [00:26:25] Speaker 04: So I'm not sure whether that plays into the ability to develop a uniform number. [00:26:31] Speaker 04: What we do know from this record is that combustion turbines, the reason that goes into why they are particularly responsive to capacity market revenues, they don't make [00:26:45] Speaker 04: most of their money from the energy market, unlike combined cycle. [00:26:48] Speaker 04: Combined cycle costs a lot more to build, fixed costs, and then makes up to 60% from the energy market revenues. [00:26:58] Speaker 04: The combustion, and I just wanted to give a couple of JA sites without belaboring the numbers, but JA 107 and 108 have the costs that Brattle came up with that show you the [00:27:11] Speaker 04: the 300 million for the combustion turbine versus the billion for the combined cycle. [00:27:17] Speaker 04: The combustion turbines, they're cheaper to build and they're faster to build, which is why they're more responsive to market signals, but they don't run as often. [00:27:28] Speaker 04: They're peaking straight. [00:27:30] Speaker 02: So I think they tend to run- But their revenue numbers were, I mean, again, it's only one component, but their revenue numbers were substantially affected by the 10% assumption. [00:27:41] Speaker 02: taken down by like a third, I think, or? [00:27:44] Speaker 04: Right. [00:27:44] Speaker 04: Which of 27% would be about 9% of their total cost. [00:27:49] Speaker 04: But so I don't have a number on, I just, since we do know that they don't run as often and they do tend to run when the system is peaking, I think that may play into what kind of costs they can bid at. [00:28:03] Speaker 04: I don't have much more on that. [00:28:04] Speaker 04: The commission really made the policy judgment based on if we've allowed it in the tariff, we don't see a basis to exclude it here just because some combustion turbines that have great access to gas supplies may have a competitive advantage in the real market. [00:28:24] Speaker 04: But for the hypothetical resource, the commission just chose not to make the assumptions about that. [00:28:32] Speaker 01: Okay, thank you. [00:28:33] Speaker 01: Let me make sure my colleagues don't have additional questions for you, Ms. [00:28:37] Speaker 01: Spanta. [00:28:39] Speaker 05: Not me. [00:28:40] Speaker 01: Okay, thank you. [00:28:41] Speaker 01: Thank you. [00:28:41] Speaker 01: Ms. [00:28:41] Speaker 01: Spanta, we'll hear from Mr. Flynn for the interveners. [00:28:46] Speaker 05: Good afternoon, Paul Flynn on behalf of PGM Interconnection. [00:28:50] Speaker 05: Starting with the 10% contingency, when we refer you to J33 and 34, which is where you find the tariff definition that was modified [00:29:02] Speaker 05: to insert the 10% rule. [00:29:07] Speaker 05: And what you will find is something called peak hour dispatch. [00:29:14] Speaker 05: And peak hour dispatch is a extensive set of rules to set administratively within this hypothetical generic combustion turbine plant will run and sell energy. [00:29:31] Speaker 05: And as you can see, there are quite a lot of standardized and simplified assumptions to capture that hypothetical circumstance for this unit. [00:29:44] Speaker 05: We're not talking about what anyone actually does in the energy market. [00:29:47] Speaker 05: We're talking about setting some reasonable standard simplifying assumptions for when that hypothetical resource will run like these four-hour blocks and the three-hour blocks and how often during the day. [00:29:59] Speaker 05: It's pretty extensive. [00:30:01] Speaker 05: And there are a lot of assumptions in there. [00:30:04] Speaker 05: My take is that FERC basically thought that, look, what mattered was, and this is what they said in their order, that what mattered was that other components of that, this is at paragraph 31 of the Rehearing Order, JA401, other components of energy offers are already included in the energy offset estimate. [00:30:29] Speaker 05: And we agree. [00:30:31] Speaker 05: that is appropriate to include the 10% adder as well, since it too is a permissible component of energy office. [00:30:36] Speaker 05: It's called an adder, but it's really to deal with the uncertainty that exists about, in particular, your fuel costs when you're making an offer in advance. [00:30:46] Speaker 02: But I haven't heard you respond to the main question I have, which is, I mean, let's say it were known that combustion turbines bids into the energy markets [00:31:00] Speaker 02: only less than 5% of the time use the adder. [00:31:04] Speaker 02: Would that not be material along with the generic notion that it's permissible for them to use it 100% of the time? [00:31:15] Speaker 05: Well, that is a hypothetical question. [00:31:18] Speaker 05: Evidence to that extent was not presented. [00:31:22] Speaker 05: And I mean, you could say 0%. [00:31:27] Speaker 05: You could say 100%. [00:31:28] Speaker 05: Or you could say, let's get a lot more complicated about how this works in the context of this one subset of this. [00:31:36] Speaker 02: All right. [00:31:36] Speaker 02: Or let's just ask, generally, the combustion turbine owners. [00:31:40] Speaker 02: And if it turns out that it's something in between, wouldn't it be more accurate? [00:31:47] Speaker 02: And accuracy is what we're looking for here. [00:31:48] Speaker 02: Wouldn't it be more accurate to say, let's put 50%? [00:31:51] Speaker 02: Let's not put the whole 10%. [00:31:53] Speaker 02: Let's put a weighted 10%. [00:31:55] Speaker 02: And we know that the economic logic [00:31:58] Speaker 02: is going to deter combustion turbines from actually making use of the up to 10% adder because it will make their already expensive energy more expensive. [00:32:11] Speaker 02: So why shouldn't it at least be, and we're not standard of review, double deference. [00:32:17] Speaker 02: We read your briefs. [00:32:18] Speaker 02: But nonetheless, it seems like there's a logical potentially dropping of the ball here. [00:32:25] Speaker 02: And I'm just looking at what your best [00:32:27] Speaker 02: answer is? [00:32:30] Speaker 05: Well, first rationale was stated in the order. [00:32:35] Speaker 05: I guess the question is, how far on every one of these assumptions does FERC have to go to establish that what is overall the demand curve, that the end of the day, it's the demand curve that is used to balance cost and reliability is just unreasonable. [00:32:57] Speaker 05: Burt did that in spades because we provided them ample evidence on that. [00:33:01] Speaker 05: And if you're willing, I'd like to turn to that next, if you'll give me the time to do that. [00:33:08] Speaker 01: Your time's expired, so I just want to make sure that you're addressing the particular question before you about the 10%. [00:33:12] Speaker 01: And I have one follow-up question, which is, do we know on the 10% if it's made use of, let's say, half the time? [00:33:23] Speaker 01: just as a ballpark. [00:33:25] Speaker 01: Do we know how much of an effect that would actually have on the demand curve? [00:33:30] Speaker 05: I don't know that we have that date. [00:33:32] Speaker 01: Would it be much? [00:33:34] Speaker 05: I don't know what effect that would have on the demand curve. [00:33:36] Speaker 05: Again, it is not counterintuitive for a seller to say, I'm legitimately concerned about whether or not my fuel costs might be uncertain. [00:33:46] Speaker 05: And so I'm going to add that contingency in there. [00:33:49] Speaker 05: So that is not economically irrational. [00:33:51] Speaker 05: They may do that. [00:33:53] Speaker 05: But we don't have evidence in record of the extent to which that is done. [00:33:58] Speaker 05: Because again, FERC looked at it in terms of a permissible energy offer, a maximum energy offer that they would permit would include these factors, which is the type of analysis they do in other cases in the capacity market in terms of what's acceptable. [00:34:12] Speaker 02: Do we know, Mr. Flynn, if there was 10% or zero, if the 10% adder were disallowed, we do know how much difference that makes in the demand curve. [00:34:20] Speaker 02: Do we not? [00:34:24] Speaker 02: It's not the 100 million that Ms. [00:34:26] Speaker 02: Roberts has been, it has to do with the choice of reference resource. [00:34:29] Speaker 02: But if we're just talking about the demand curve, the change in the price based on including the 10% in the net cost. [00:34:43] Speaker 05: I'm not sure, Your Honor. [00:34:45] Speaker 05: Again, it's a modeling effort. [00:34:47] Speaker 05: specific to the peak hour dispatch, because you're saying under this entire set of assumptions, if you also assume that they do not have this extra bit in their offer, what happens every hour of the year in terms of how they clear in the market? [00:35:04] Speaker 05: It's not a simple calculation that you can just do the math and say, oh, it's this. [00:35:08] Speaker 05: You'd have to run the model. [00:35:09] Speaker 02: They're only in the market a very few hours. [00:35:14] Speaker 02: and we have presumably past performance information. [00:35:19] Speaker 02: Maybe we can ask Ms. [00:35:20] Speaker 02: Roberts when she's back before us. [00:35:23] Speaker 02: But yeah, it would be helpful. [00:35:24] Speaker 02: I mean, if the chief is not averse to have you talk about the first issue as well. [00:35:30] Speaker 02: I would love to. [00:35:31] Speaker 01: And again- Why don't you just take a minute to do that. [00:35:34] Speaker 01: Sure. [00:35:36] Speaker 05: Could I draw your attention to, it is joint appendix 189. [00:35:46] Speaker 05: which is Brattle's report on the demand curve through Table 11. [00:35:58] Speaker 05: This is what you were referring to earlier in the argument, Judge Collard. [00:36:05] Speaker 05: Brattle does Monte Carlo simulations that look at a thousand different slightly varying scenarios and come up with an average and a projection. [00:36:16] Speaker 05: for reliability and for cost. [00:36:18] Speaker 05: And they do that in this case for six different curves. [00:36:22] Speaker 05: Two of them were existing curves. [00:36:24] Speaker 05: So really there's one combustion turbine that was new and three combined cycles that were new. [00:36:35] Speaker 05: And if you made it to that table, if I could draw your attention to the fourth column in from the left, which is where the costs are. [00:36:45] Speaker 02: I'm sorry, tell me again what page you're on. [00:36:47] Speaker 02: I don't think I'm on the right. [00:36:48] Speaker 02: 189. [00:36:48] Speaker 02: 189. [00:36:49] Speaker 02: Thank you. [00:36:57] Speaker 05: So when you get to that table and you look at the cost column, which is the fourth set of numbers in, you'll see a very tight range of costs. [00:37:06] Speaker 05: It's on the order of 7.9 billion to 8 billion, more or less. [00:37:11] Speaker 05: Captures all of the different curves that were considered. [00:37:15] Speaker 05: And specifically the curve that FERC approved is B is in boy at 8.06 million. [00:37:24] Speaker 05: And the curve that petitioners have advocated is D is in David, 7.97 billion. [00:37:34] Speaker 05: So for costs, we're talking the difference of about 1% in these money follow simulations of future costs and future reliability. [00:37:44] Speaker 05: So we're not saying, oh my gosh, they're gonna pay an extra $90 million a year coming out of someone's pocket. [00:37:52] Speaker 05: This is a comparison of modeling scenarios. [00:37:57] Speaker 05: And there's only a 1% difference between the two. [00:38:00] Speaker 05: And then you look over to the column, which is second from the right, and that shows the number of percentages for the different curves, including how frequently [00:38:11] Speaker 05: each of those curves is expected to produce a result below the reliability requirement. [00:38:18] Speaker 05: And you see for B, it's 0%. [00:38:21] Speaker 05: And for D, it's 5%. [00:38:22] Speaker 05: So there's a bit of a difference there. [00:38:23] Speaker 05: There's a bit of a difference which is adverse from a reliability perspective. [00:38:29] Speaker 05: If you look at the column that is called average LOL, it's like in the middle. [00:38:41] Speaker 05: and then stress L-O-L-E. [00:38:44] Speaker 05: Stress L-O-E says, what if they've, it's like stress testing anything. [00:38:47] Speaker 05: What if one of our assumptions is off by a bit? [00:38:51] Speaker 05: You'll see that of the three combined cycles, which are the last three numbers, two of them are above a 10th of a percent, which means they violate on an average basis, the expectation that you'll only have one loss of load every 10 years. [00:39:07] Speaker 05: So as a group, the CDCs clearly do worse. [00:39:11] Speaker 05: than the combustion turbines. [00:39:14] Speaker 05: So what does FERC have to say about all this? [00:39:22] Speaker 05: FERC says, when they briefly note in their opening to the discussion of the VRR curve, which is where this appears, all this stuff about the cost of a combustion turbine versus the reliability of a combustion turbine in a combined cycle, all appears in FERC's discussion of the VRR curve. [00:39:40] Speaker 05: not of the reference resource. [00:39:42] Speaker 05: But that's where the numbers of a hundred million dollars that petitioners have cited, that's where that comes from. [00:39:49] Speaker 05: So FERC, in that brief introduction, at paragraph 17 of the initial order, notes PGM's statement that, all of the annual cost projections were clustered fairly close together, with the total customer cost difference over all curves ranging only a few percent. [00:40:08] Speaker 05: That's one of the few facts they cite in that opening. [00:40:11] Speaker 05: And then they say, in paragraph 16, PGM's proposed changes result in a curve that means PGM's reliability needs any reasonable total cost to load, which is the numbers we were just looking at. [00:40:31] Speaker 05: And then similarly, in paragraph 20, the J301, Perk found that PGM's analysis [00:40:38] Speaker 05: Excuse me, was sufficient to meet the requirements, which tariff, which is designed to ensure the proposed demand curve meets PJM's reliability needs at a reasonable total cost to load. [00:40:53] Speaker 05: And we know they were talking about the Monte Carlo simulation model when they say that, because in the very next breath, they say that the public interest entities, which is the petitioner group, [00:41:06] Speaker 02: Let me ask you, Mr. Flint, because I know we're over time, and just going back to the 10%. [00:41:15] Speaker 02: So PJM didn't actually investigate the issue before adopting the Adder, right? [00:41:19] Speaker 02: I mean, Brattle had said it's sort of difficult to study, but it might be a good thing for further investigation. [00:41:26] Speaker 02: And PJM chose not to do that investigation, right? [00:41:31] Speaker 05: It was more of a normative call on the basis of this is [00:41:36] Speaker 05: element of what people can offer in the energy market and you shouldn't just exclude it and so we included it. [00:41:42] Speaker 02: Right and there was no reasoning in so doing that making a more fine-tuned factual judgment was going to be too difficult and and too much of a going down a rabbit hole wasn't like well it'd be great if we had that information [00:41:56] Speaker 02: But we, on balance, decide that it's not going to be worth the candle to do that further investigation. [00:42:05] Speaker 02: It just was like, this is permissible and that's enough. [00:42:09] Speaker 05: Yeah, I don't know that there was a sense that they said that it would be very easy to make that determination. [00:42:14] Speaker 02: I don't think that- No, no, they didn't. [00:42:16] Speaker 02: They said that it's a little tricky, but maybe it's worth further study. [00:42:21] Speaker 02: And that was not taken up by- That's what Brattle said. [00:42:24] Speaker 05: Yes, right. [00:42:25] Speaker 05: But I don't know that PJM said, no, it's not worth it. [00:42:31] Speaker 02: Exactly. [00:42:31] Speaker 02: Didn't say that. [00:42:32] Speaker 02: Just said it's authorized and therefore we're going with it. [00:42:36] Speaker 05: And it's better to include it than not. [00:42:39] Speaker 05: And so that was proposed to be included in FERC accepted on that basis as part of a lawful offer in the energy market, which is a rational sort of approach. [00:42:49] Speaker 01: OK. [00:42:49] Speaker 01: All right. [00:42:51] Speaker 01: Thank you. [00:42:51] Speaker 01: Let me make sure my colleagues don't have additional questions for you, Mr. Flynn, at this time. [00:42:55] Speaker 01: Thank you. [00:42:56] Speaker 01: Thank you. [00:42:57] Speaker 01: Mr. Roberts, we'll give you three minutes for your rebuttal, please. [00:43:01] Speaker 03: I appreciate it. [00:43:03] Speaker 03: Thank you, Your Honor. [00:43:04] Speaker 03: So I first want to pick up on the 10% adder issue briefly. [00:43:08] Speaker 03: You're absolutely right Judge Pillard that we don't know how often the 10% adder is used. [00:43:12] Speaker 03: And FERC has a tool at its disposal to get more information in these kinds of situations. [00:43:17] Speaker 03: It can issue a deficiency letter to PJM to ask them to submit additional information. [00:43:21] Speaker 03: FERC did that on a different issue in the case, could have done it on 10%, but I think just decided that that level of accuracy wasn't important, didn't use the tool at its disposal. [00:43:33] Speaker 03: And this whole 10% adder issue, which as you've noted, [00:43:36] Speaker 03: can affect this assumption, the single assumption can affect the energy revenues that are earned by the reference resource by one third just shows why it's hard to estimate the cost and revenues of a combustion turbine and one reason why it doesn't pass muster under that three part test. [00:43:56] Speaker 03: And Joint Appendix 141, Brattle discusses these uncertainties about gas procurement costs being one reason why it's so hard to determine the costs and revenues for a combustion turbine resource. [00:44:12] Speaker 03: Next, I'd like to just touch on the evidence that Mr. Flynn was discussing with this table in the Brattle report showing the frequency below the reliability requirement. [00:44:21] Speaker 03: I want to stress that FERC has said that that reliability requirement must be met on average, not in every single year. [00:44:27] Speaker 03: So the column he was pointing to about this is the percentage likelihood below the reliability requirement is on an every year basis, which is not the standard that FERC has set. [00:44:37] Speaker 03: And this goes to something that Miss Banto was saying, of course, FERC can allow rates to increase to ensure reliability, but it needs to explain why it's doing so, and it needs to be specific. [00:44:49] Speaker 03: So if FERC wants to depart from its prior determination that the reliability standard is one in 10 on average, [00:44:57] Speaker 03: I suppose that it could do so but it would need to do so consciously and explain why the additional costs that are being imposed on consumers are now necessary in its view, rather than adhering to the previous formulation of the reliability standard that is established. [00:45:13] Speaker 03: And finally, I want to note that the language quoted by both Ms. [00:45:19] Speaker 03: Banta and Mr. Flynn about FERC's consideration of cost is really lip service to this requirement that they look at the cost. [00:45:26] Speaker 03: Simply saying the word cost or this is at a reasonable cost does not meet the requirement for reasoned decision making where very specific arguments have been made in a request for rehearing. [00:45:36] Speaker 03: that the specific costs are not worth the sort of specific incremental reliability benefit that consumers would receive. [00:45:46] Speaker 03: So FERC just didn't ever talk about what's the incremental reliability benefit of sticking with the CT, what's the incremental cost associated with that, and make an express decision that that cost was worth that cost. [00:45:58] Speaker 03: So just generally referring to this is at a reasonable cost, [00:46:02] Speaker 03: It doesn't pass master. [00:46:04] Speaker 03: So, so I have we respectfully asked the court to remand the four quarters in question, based on the flaws in the orders that we've noted in our briefs. [00:46:12] Speaker 03: Thank you. [00:46:13] Speaker 01: Thank you, counsel. [00:46:14] Speaker 01: Thank you to all counsel will take this case under submission.